| UID | Task Name | Duration | Start | Finish | % Complete |
| 1 | Proton Plan | 951 d | 9/30/04 | 7/16/08 | 23% |
| 2 | Linac Upgrades | 774 d | 12/15/04 | 1/18/08 | 18% |
| 6 | Linac PA Vulnerability | 666 d | 12/15/04 | 8/10/07 | 21% |
| 281 | Linac PA Task Force | 416 d | 12/15/04 | 8/11/06 | 35% |
| 26 | Linac Task Force: Phase 1 | 39 d | 12/15/04 | 2/14/05 | 100% |
| 27 | Linac Task Force Phase 1 Report Issued | 0 d | 2/14/05 | 2/14/05 | 100% |
| 34 | Linac Task Force: Phase 2 | 97 d | 2/15/05 | 6/30/05 | 100% |
| 35 | Linac Task Force Phase 2 Report Issued | 0 d | 6/30/05 | 6/30/05 | 100% |
| 36 | Linac Task Force 2 | 250 d | 8/15/05 | 8/11/06 | 0% |
| 37 | Linac Task Force 2 Complete | 0 d | 8/11/06 | 8/11/06 | 0% |
| 282 | 7835 Purchase | 272 d | 2/18/05 | 3/20/06 | 17% |
| 28 | Linac Task Force PA Prepare Order | 21 d | 2/18/05 | 3/18/05 | 100% |
| 29 | Linac Task Force PA Award Order | 1 d | 3/21/05 | 3/21/05 | 100% |
| 30 | Linac Task Force PA Delivery | 105 d | 10/14/05 | 3/20/06 | 0% |
| 799 | Thales Prototype Facility | 250 d | 8/14/06 | 8/10/07 | 0% |
| 8 | Linac Quad Power Supplies | 765 d | 1/3/05 | 1/18/08 | 25% |
| 211 | Linac Quad PS: Design & Prototype | 149 d | 1/3/05 | 8/2/05 | 100% |
| 236 | Linac Quad PS Conceptual Specifications | 148 d | 1/3/05 | 8/1/05 | 100% |
| 237 | Linac Quad PS Conceptual 300 amp Test | 85 d | 4/1/05 | 8/1/05 | 100% |
| 415 | Linac Quad PS Conceptual Review Prototype | 1 d | 8/2/05 | 8/2/05 | 100% |
| 238 | Linac Quad PS Conceptual Design | 87 d | 3/1/05 | 6/30/05 | 100% |
| 239 | Linac Quad PS Conceptual Inductor Design | 87 d | 3/1/05 | 6/30/05 | 100% |
| 777 | Linac Quad PS Project Decision | 0 d | 8/1/05 | 8/1/05 | 100% |
| 240 | Linac Quad PS Upgrade - Card Replacement | 574 d | 10/3/05 | 1/18/08 | 0% |
| 778 | Linac Quad PS Upgrade Design | 170 d | 10/3/05 | 6/7/06 | 0% |
| 779 | Linac Quad PS Upgrade Drafting | 110 d | 2/2/06 | 7/7/06 | 0% |
| 780 | Linac Quad PS Upgrade Procurement | 420 d | 4/3/06 | 11/28/07 | 0% |
| 708 | Linac Quad PS Upgrade Test | 250 d | 12/18/06 | 12/14/07 | 0% |
| 709 | Linac Quad PS Upgrade Install | 250 d | 1/23/07 | 1/18/08 | 0% |
| 710 | Linac Quad PS Upgrade Installation Complete | 0 d | 1/18/08 | 1/18/08 | 0% |
| 459 | 200 Mhz LLRF Upgrade | 522 d | 9/1/05 | 10/1/07 | 0% |
| 786 | 200 Mhz LLRF Engineering | 271 d | 9/1/05 | 9/29/06 | 0% |
| 460 | 200 Mhz LLRF Modeling | 125 d | 9/1/05 | 3/6/06 | 0% |
| 468 | 200 Mhz LLRF Engineering | 250 d | 10/3/05 | 9/29/06 | 0% |
| 781 | 200 Mhz LLRF Design Review | 1 d | 2/7/06 | 2/7/06 | 0% |
| 787 | 200 Mhz LLRF Procure/Assy/Test/Install | 232 d | 9/29/06 | 8/31/07 | 0% |
| 712 | 200 Mhz LLRF Procurement | 84 d | 10/2/06 | 2/5/07 | 0% |
| 713 | 200 Mhz LLRF Assembly | 125 d | 9/29/06 | 4/2/07 | 0% |
| 714 | 200 Mhz LLRF Testing | 125 d | 11/30/06 | 5/31/07 | 0% |
| 715 | 200 Mhz LLRF Installation | 20 d | 8/6/07 | 8/31/07 | 0% |
| 718 | 200 Mhz LLRF Commissioning | 20 d | 9/4/07 | 10/1/07 | 0% |
| 716 | 200 Mhz LLRF Installation Complete | 0 d | 10/1/07 | 10/1/07 | 0% |
| 3 | Booster Upgrades | 951 d | 9/30/04 | 7/16/08 | 17% |
| 737 | Booster RF Duty Cycle Limits & Means of Improving Booster RF Reliability for 9Hz Operation | 43 d | 8/8/05 | 10/6/05 | 0% |
| 732 | Feasibility of Booster RF Operating @ 9Hz | 43 d | 8/8/05 | 10/6/05 | 0% |
| 9 | Determine Duty Cycle Limit for Booster West Gallery Transformer (Y02-US-01) | 10 d | 8/8/05 | 8/19/05 | 0% |
| 733 | Investigate Reprogramming Ferrite Bias Program to Reduce RMS Current | 21 d | 8/8/05 | 9/6/05 | 0% |
| 734 | Determine Duty Cycle Limit for Booster West Gallery Ferrite Bias Supply Transformers | 21 d | 8/8/05 | 9/6/05 | 0% |
| 735 | Review Duty Cycle Limit Study Results w/FESS Engineering Electrical Consultant | 1 d | 9/7/05 | 9/7/05 | 0% |
| 740 | Document Findings & Recommendations w/Report | 21 d | 9/8/05 | 10/6/05 | 0% |
| 741 | Booster RF Report Issued | 0 d | 10/6/05 | 10/6/05 | 0% |
| 736 | Strategies for Improving Booster RF Reliability @ 9Hz | 21 d | 8/8/05 | 9/6/05 | 0% |
| 738 | Review Station Down Time for Determining Equip Vulnerability | 5 d | 8/8/05 | 8/12/05 | 0% |
| 739 | Develop Action Plan to Improve Reliability | 21 d | 8/8/05 | 9/6/05 | 0% |
| 10 | OrBump System | 328 d | 9/30/04 | 1/25/06 | 68% |
| 38 | OrBump System Magnets Design & Production | 283 d | 9/30/04 | 11/14/05 | 76% |
| 202 | OrBump Magnet TD Division FY04 Costs | 1 d | 9/30/04 | 9/30/04 | 100% |
| 139 | OrBump Magnets | 255 d | 10/1/04 | 10/6/05 | 85% |
| 137 | Design OrBump Magnets (3+3 spares) | 240 d | 10/1/04 | 9/15/05 | 97% |
| 138 | Procure Components & Tooling for OrBump Magnets (3+3 spares) | 157 d | 2/4/05 | 9/15/05 | 94% |
| 100 | Assemble, Test & Rework 1st Article OrBump Magnet | 240 d | 10/1/04 | 9/15/05 | 90% |
| 101 | Assemble Final 5 OrBump Magnets (2+3 spares) | 144 d | 2/23/05 | 9/15/05 | 58% |
| 102 | Test Final 5 OrBump Magnets (2+3 spares) (AD) | 15 d | 9/16/05 | 10/6/05 | 0% |
| 305 | OrBump Magnets Ready for Install on Girder | 0 d | 10/6/05 | 10/6/05 | 0% |
| 142 | OrBump Stripline | 136 d | 4/1/05 | 10/12/05 | 59% |
| 143 | Design OrBump Stripline | 105 d | 4/1/05 | 8/29/05 | 80% |
| 144 | Procure OrBump Stripline | 22 d | 8/22/05 | 9/21/05 | 0% |
| 145 | Assemble OrBump Stripline | 15 d | 9/22/05 | 10/12/05 | 0% |
| 306 | OrBump Stripline Assy Complete | 0 d | 10/12/05 | 10/12/05 | 0% |
| 146 | OrBump Girder | 159 d | 4/1/05 | 11/14/05 | 45% |
| 147 | Design OrBump Girder Assembly | 100 d | 4/1/05 | 8/22/05 | 75% |
| 148 | Procure OrBump Girder Assembly | 45 d | 7/29/05 | 9/30/05 | 5% |
| 140 | Mount OrBump Components on Girder | 22 d | 10/7/05 | 11/7/05 | 0% |
| 141 | Survey OrBump Magnets & Girder | 5 d | 11/8/05 | 11/14/05 | 0% |
| 307 | OrBump Girder Assy Complete | 0 d | 11/14/05 | 11/14/05 | 0% |
| 39 | OrBump System Power Supply | 204 d | 1/25/05 | 11/9/05 | 58% |
| 40 | OrBump P.S. Specifications | 5 d | 1/25/05 | 1/31/05 | 100% |
| 41 | OrBump P.S. Simulations | 10 d | 2/1/05 | 2/14/05 | 100% |
| 404 | OrBump P.S. Design Review Preparation | 21 d | 5/9/05 | 6/7/05 | 100% |
| 405 | OrBump P.S. Design Review | 1 d | 6/15/05 | 6/15/05 | 100% |
| 45 | OrBump P.S. Cabinet Layout | 65 d | 6/1/05 | 8/31/05 | 50% |
| 46 | OrBump P.S. General Procurement | 130 d | 3/1/05 | 8/31/05 | 94% |
| 42 | OrBump P.S. Procure Capacitors | 141 d | 2/15/05 | 9/1/05 | 20% |
| 44 | OrBump Charging Power Supply Assembly | 101 d | 4/11/05 | 8/31/05 | 90% |
| 47 | OrBump P.S. Cabinet Assembly | 25 d | 9/27/05 | 10/31/05 | 0% |
| 43 | OrBump P.S. Assemble Controls | 70 d | 6/17/05 | 9/26/05 | 32% |
| 278 | OrBump P.S. Initial Testing | 7 d | 11/1/05 | 11/9/05 | 0% |
| 309 | OrBump Power Supply Ready for Installation | 0 d | 11/9/05 | 11/9/05 | 0% |
| 342 | OrBump Syst Installation | 163 d | 5/2/05 | 12/21/05 | 56% |
| 175 | Installation | 21 d | 11/10/05 | 12/12/05 | 0% |
| 176 | Install OrBump Power Supply | 7 d | 11/10/05 | 11/18/05 | 0% |
| 177 | Install OrBump Magnet System | 8 d | 11/16/05 | 11/29/05 | 0% |
| 178 | Pull Cables/Terminate/Install Head | 2 d | 11/23/05 | 11/28/05 | 0% |
| 180 | OrBump System Survey | 7 d | 11/30/05 | 12/8/05 | 0% |
| 308 | OrBump System Installation Complete | 0 d | 12/12/05 | 12/12/05 | 0% |
| 386 | 400 MEV Line Reconfiguration | 163 d | 5/2/05 | 12/21/05 | 71% |
| 387 | 400 MeV Beamline Design | 60 d | 5/2/05 | 7/26/05 | 100% |
| 388 | 400 MeV Optics Design | 21 d | 5/2/05 | 5/31/05 | 100% |
| 389 | 400 MeV Beam Sheet | 2 d | 7/14/05 | 7/15/05 | 100% |
| 456 | 400 MeV Drawing | 7 d | 7/18/05 | 7/26/05 | 100% |
| 452 | 400 MeV Alignment | 137 d | 6/1/05 | 12/14/05 | 86% |
| 453 | 400 MeV Beam Sheet Based on As-found '04 | 30 d | 6/1/05 | 7/13/05 | 100% |
| 454 | 400 MeV Delimiter New Stationing | 1 d | 11/23/05 | 11/23/05 | 0% |
| 455 | 400 MeV Survey | 4 d | 12/9/05 | 12/14/05 | 0% |
| 390 | 400 MeV Installation | 31 d | 11/7/05 | 12/21/05 | 0% |
| 391 | 400 MeV Vent Vacuum/Disconnect Electrical/LCW | 2 d | 11/7/05 | 11/8/05 | 0% |
| 442 | 400 MeV Remove Magnets & Other Components | 5 d | 11/9/05 | 11/15/05 | 0% |
| 445 | 400 MeV Install Magnets & Other Components | 5 d | 11/30/05 | 12/6/05 | 0% |
| 446 | 400 MeV Connect Vacuum System/Pump Down/Leak Check | 3 d | 12/15/05 | 12/19/05 | 0% |
| 447 | 400 MeV Connect Water/Electrical | 2 d | 12/20/05 | 12/21/05 | 0% |
| 448 | 400 MeV Electrical | 2 d | 12/7/05 | 12/8/05 | 0% |
| 449 | 400 MeV Isolate MH2 Power Cables | 1 d | 12/7/05 | 12/7/05 | 0% |
| 450 | 400 MeV MH2 PS Change Gain | 1 d | 12/8/05 | 12/8/05 | 0% |
| 789 | Commission OrBump System | 10 d | 1/11/06 | 1/25/06 | 0% |
| 791 | OrBump System Commissioned | 0 d | 1/25/06 | 1/25/06 | 0% |
| 11 | Corrector System | 889 d | 1/4/05 | 7/16/08 | 2% |
| 74 | Corrector Magnets Design & Prototype | 387 d | 1/4/05 | 7/17/06 | 16% |
| 800 | Initial Corrector Prototype Design & Fab | 146 d | 1/4/05 | 7/29/05 | 100% |
| 60 | Design Corrector Prototype | 223 d | 8/1/05 | 6/20/06 | 0% |
| 61 | Corrector Prototype Procurement | 254 d | 3/1/05 | 3/3/06 | 2% |
| 67 | Corrector Prototype Production | 294 d | 4/12/05 | 6/12/06 | 2% |
| 73 | Corrector Prototype Test | 63 d | 4/18/06 | 7/17/06 | 0% |
| 310 | Corrector Prototype Magnet Complete | 0 d | 7/17/06 | 7/17/06 | 0% |
| 698 | Corr Prototype Design Complete | 0 d | 6/20/06 | 6/20/06 | 0% |
| 75 | Vert Corr Magnets Production | 270 d | 7/6/06 | 8/1/07 | 0% |
| 339 | Vert Corr Magnets Design & Procurement | 236 d | 7/19/06 | 6/26/07 | 0% |
| 184 | Design Vert Corr Production Units (24) | 10 d | 7/19/06 | 8/1/06 | 0% |
| 76 | Procure Vert Corr Components | 226 d | 8/2/06 | 6/26/07 | 0% |
| 340 | Vert Corr Magnets Fab & Test | 270 d | 7/6/06 | 8/1/07 | 0% |
| 77 | Fabricate Vert Corr Production Units (24) | 149 d | 12/13/06 | 7/18/07 | 0% |
| 185 | Test Vert Corr Production Units | 270 d | 7/6/06 | 8/1/07 | 0% |
| 222 | Vert Corr Integrated BPMs | 140 d | 12/13/06 | 7/5/07 | 0% |
| 312 | Vert Corr Magnets Ready for Installation | 0 d | 8/1/07 | 8/1/07 | 0% |
| 469 | Corrector PS Design & Prototype | 286 d | 8/1/05 | 9/19/06 | 0% |
| 470 | Magnet Power Supplies -- 50 Amp, PS1 | 236 d | 8/1/05 | 7/10/06 | 0% |
| 471 | PS1: Specification | 20 d | 8/1/05 | 8/26/05 | 0% |
| 472 | PS1: Identify Vendors | 4 d | 8/29/05 | 9/1/05 | 0% |
| 473 | PS1: Vendor Specification Review | 1 d | 9/16/05 | 9/16/05 | 0% |
| 474 | PS1: Request For Inquiry Bids | 1 d | 9/23/05 | 9/23/05 | 0% |
| 475 | PS1: Procurement of Vendor Model | 1 d | 12/20/05 | 12/20/05 | 0% |
| 476 | PS1: Prototype In-House PS Design | 120 d | 9/19/05 | 3/14/06 | 0% |
| 477 | PS1: Prototype Fabrication | 1 d | 5/23/06 | 5/23/06 | 0% |
| 478 | PS1: Prototype Testing | 30 d | 5/24/06 | 7/6/06 | 0% |
| 479 | PS1: Approval For Production | 2 d | 7/7/06 | 7/10/06 | 0% |
| 480 | Magnet Power Supplies -- 5 Amp, PS2 | 136 d | 8/1/05 | 2/16/06 | 0% |
| 481 | PS2: Specification | 20 d | 8/1/05 | 8/26/05 | 0% |
| 482 | PS2: Identify Vendors | 4 d | 8/29/05 | 9/1/05 | 0% |
| 483 | PS2: Vendor Specification Review | 1 d | 9/16/05 | 9/16/05 | 0% |
| 484 | PS2: Request For Inquiry Bids | 1 d | 9/23/05 | 9/23/05 | 0% |
| 485 | PS2: Integration of PS into system | 20 d | 9/19/05 | 10/14/05 | 0% |
| 486 | PS2: Prototype Fabrication | 1 d | 12/29/05 | 12/29/05 | 0% |
| 487 | PS2: Prototype Testing | 30 d | 1/3/06 | 2/14/06 | 0% |
| 488 | PS2: Approval For Production | 2 d | 2/15/06 | 2/16/06 | 0% |
| 489 | Corrector Controller Design & Prototype, PCC | 74 d | 2/1/06 | 5/15/06 | 0% |
| 490 | CC: Specification | 4 d | 2/1/06 | 2/6/06 | 0% |
| 491 | CC: Prototype Schematic Layout | 10 d | 2/7/06 | 2/20/06 | 0% |
| 492 | CC: Prototype Parts Procurement | 1 d | 4/3/06 | 4/3/06 | 0% |
| 493 | CC: Prototype PCB Layout | 20 d | 2/21/06 | 3/20/06 | 0% |
| 494 | CC: Prototype PCB Fabrication | 1 d | 4/10/06 | 4/10/06 | 0% |
| 495 | CC: Prototype Assembly, 5 Units | 3 d | 4/11/06 | 4/13/06 | 0% |
| 496 | CC: Prototype Testing | 10 d | 4/14/06 | 4/27/06 | 0% |
| 497 | CC: Prototype Approval | 2 d | 4/28/06 | 5/1/06 | 0% |
| 498 | CC: Production Schematic Revisions | 4 d | 5/2/06 | 5/5/06 | 0% |
| 499 | CC: Teststand Assembly | 10 d | 5/2/06 | 5/15/06 | 0% |
| 500 | Local Display Design & Prototype | 63 d | 6/21/06 | 9/19/06 | 0% |
| 501 | DD: Specification & Layout | 15 d | 6/21/06 | 7/12/06 | 0% |
| 502 | DD: Hardware / Enclosure Design | 2 d | 7/13/06 | 7/14/06 | 0% |
| 503 | DD: Prototype Schematic Layout | 10 d | 7/17/06 | 7/28/06 | 0% |
| 504 | DD: Prototype Parts Procurement | 1 d | 9/11/06 | 9/11/06 | 0% |
| 505 | DD: Prototype PCB Layout | 10 d | 7/31/06 | 8/11/06 | 0% |
| 506 | DD: Prototype PCB Fabrication | 1 d | 9/1/06 | 9/1/06 | 0% |
| 507 | DD: Prototype Assembly, 2 Units | 2 d | 9/12/06 | 9/13/06 | 0% |
| 508 | DD: Prototype Testing | 1 d | 9/14/06 | 9/14/06 | 0% |
| 509 | DD: Prototype Approval | 1 d | 9/15/06 | 9/15/06 | 0% |
| 510 | DD: Production Schematic Revisions | 2 d | 9/18/06 | 9/19/06 | 0% |
| 511 | Verticle Corrector PS Fabrication | 209 d | 4/27/06 | 2/27/07 | 0% |
| 512 | Vert Corr PS Production -- 50 Amp, PS1 | 158 d | 7/11/06 | 2/27/07 | 0% |
| 513 | Vert Corr PS1: Production Specification & Vendor Selection | 10 d | 7/11/06 | 7/24/06 | 0% |
| 514 | Vert Corr PS1: Production Oversight | 100 d | 7/25/06 | 12/14/06 | 0% |
| 748 | Vert Corr PS1: Procurement Awarded | 1 d | 7/24/06 | 7/24/06 | 0% |
| 515 | Vert Corr PS1: Production Order Fabrication & Delivery, 120 Units | 48 d | 9/20/06 | 11/28/06 | 0% |
| 516 | Vert Corr PS1: Production Order Testing | 48 d | 12/15/06 | 2/27/07 | 0% |
| 517 | Vert Corr PS Production -- 5 Amp, PS2 | 25 d | 4/27/06 | 6/1/06 | 0% |
| 518 | Vert Corr PS2: Production Order Fabrication, 24 Units | 1 d | 4/27/06 | 4/27/06 | 0% |
| 519 | Vert Corr PS2: Production Order Testing | 24 d | 4/28/06 | 6/1/06 | 0% |
| 520 | Verticle Corrector Installation | 494 d | 2/1/06 | 1/18/08 | 0% |
| 521 | Vert Corr PS & Controls Rack Assembly | 390 d | 2/1/06 | 8/16/07 | 0% |
| 522 | CAMAC Vert Corr Controller, CC | 75 d | 5/8/06 | 8/22/06 | 0% |
| 523 | Vert Corr CC: Production Parts Procurement, 36 Units | 1 d | 6/19/06 | 6/19/06 | 0% |
| 524 | Vert Corr CC: Production PCB Layout | 10 d | 5/8/06 | 5/19/06 | 0% |
| 525 | Vert Corr CC: Production PCB Fabrication, 36 Units | 1 d | 6/19/06 | 6/19/06 | 0% |
| 526 | Vert Corr CC: Production Assembly, 36 Units | 40 d | 6/20/06 | 8/15/06 | 0% |
| 527 | Vert Corr CC: Production Testing | 40 d | 6/27/06 | 8/22/06 | 0% |
| 528 | Vert Corr Local Displays & Diagnostics, DD | 59 d | 9/18/06 | 12/11/06 | 0% |
| 529 | Vert Corr DD: Production Parts Procurement, 36 units | 1 d | 10/31/06 | 10/31/06 | 0% |
| 530 | Vert Corr DD: Production PCB Layout | 5 d | 9/20/06 | 9/26/06 | 0% |
| 531 | Vert Corr DD: Production PCB Fabrication, 36 Units | 1 d | 10/17/06 | 10/17/06 | 0% |
| 532 | Vert Corr DD: Production Assembly, 36 Units | 9 d | 11/1/06 | 11/13/06 | 0% |
| 533 | Vert Corr DD: Production Testing | 18 d | 11/14/06 | 12/11/06 | 0% |
| 534 | Vert Corr DD: Documentation | 20 d | 9/18/06 | 10/13/06 | 0% |
| 535 | Vert Corr Rack Installation, RI | 390 d | 2/1/06 | 8/16/07 | 0% |
| 536 | Vert Corr RI: Identify New Rack Locations | 2 d | 7/19/06 | 7/20/06 | 0% |
| 537 | Vert Corr RI: Specify Rack Layout & Cooling | 10 d | 7/21/06 | 8/3/06 | 0% |
| 538 | Vert Corr RI: Create Drawings for Rack Layout | 5 d | 8/4/06 | 8/10/06 | 0% |
| 539 | Vert Corr RI: Prepare New Rack Locations | 5 d | 2/1/06 | 2/7/06 | 0% |
| 540 | Vert Corr RI: Transport Racks from Storage | 5 d | 2/8/06 | 2/14/06 | 0% |
| 541 | Vert Corr RI: Prepare Racks with Equip. Support Hardware | 5 d | 8/11/06 | 8/17/06 | 0% |
| 542 | Vert Corr RI: AC Power Installation | 21 d | 8/18/06 | 9/18/06 | 0% |
| 543 | Vert Corr RI: Install Rack Cooling | 5 d | 9/19/06 | 9/25/06 | 0% |
| 544 | Vert Corr RI: Install Bulk Power Supplies, 6 each 15kW Units | 5 d | 9/19/06 | 9/25/06 | 0% |
| 545 | Vert Corr RI: Install Power Amplifiers | 10 d | 2/28/07 | 3/13/07 | 0% |
| 546 | Vert Corr RI: Install Controls & Diagnostic Equip. | 40 d | 3/14/07 | 5/8/07 | 0% |
| 547 | Vert Corr RI: Power Amplifier Test Design & Hazard Analysis | 10 d | 8/11/06 | 8/24/06 | 0% |
| 548 | Vert Corr RI: Test Interlocks | 10 d | 5/9/07 | 5/22/07 | 0% |
| 549 | Vert Corr RI: Test Power Amplifiers w/Load | 40 d | 5/23/07 | 7/19/07 | 0% |
| 550 | Vert Corr RI: Test Controls | 20 d | 7/20/07 | 8/16/07 | 0% |
| 551 | Vert Corr Cabling, CBL | 95 d | 7/11/06 | 11/21/06 | 0% |
| 552 | Vert Corr CBL: Specify Power Cables & Connectors | 4 d | 7/11/06 | 7/14/06 | 0% |
| 553 | Vert Corr CBL: Bid & Procure Power Cables | 1 d | 9/25/06 | 9/25/06 | 0% |
| 554 | Vert Corr CBL: Procure Power Cable Connectors | 1 d | 11/6/06 | 11/6/06 | 0% |
| 555 | Vert Corr CBL: Power Cable is Delivered | 1 d | 11/7/06 | 11/7/06 | 0% |
| 556 | Vert Corr CBL: Pull Power Cables from Racks to Magnets | 10 d | 11/8/06 | 11/21/06 | 0% |
| 557 | Vert Corr CBL: Specifying Control Cables & Connectors | 8 d | 7/11/06 | 7/20/06 | 0% |
| 558 | Vert Corr CBL: Procure Control Cable & Connectors | 1 d | 8/31/06 | 8/31/06 | 0% |
| 559 | Vert Corr CBL: Routing Control Cables | 4 d | 9/1/06 | 9/7/06 | 0% |
| 560 | Vert Corr CBL: Terminating Control Cables | 40 d | 9/8/06 | 11/2/06 | 0% |
| 561 | Vert Corrector Magnet Installation | 395 d | 6/21/06 | 1/18/08 | 0% |
| 562 | Vert Corr Booster Modification (BM) | 294 d | 6/21/06 | 8/21/07 | 0% |
| 567 | Vert Corr BM: Design of New LS Spool Piece | 10 d | 6/21/06 | 7/5/06 | 0% |
| 750 | Vert Corr BM: Procure & Machining of Initial LS Spool Piece | 1 d | 8/30/06 | 8/30/06 | 0% |
| 751 | Vert Corr BM: Assembly of Initial LS Spool Piece | 4 d | 8/31/06 | 9/6/06 | 0% |
| 752 | Vert Corr BM: LS Initial Spool Piece Examination in Booster Enclosure | 6 d | 9/7/06 | 9/14/06 | 0% |
| 753 | Vert Corr BM: Develop Drawings for Long Straight | 10 d | 9/15/06 | 9/28/06 | 0% |
| 568 | Vert Corr BM: Procure & Machining of LS Spool Piece Components | 1 d | 9/29/06 | 9/29/06 | 0% |
| 569 | Vert Corr BM: Enclosure Installation Hazard Analysis | 12 d | 7/6/06 | 7/21/06 | 0% |
| 570 | Vert Corr BM: Enclosure Work Safety Review | 2 d | 7/24/06 | 7/25/06 | 0% |
| 572 | Vert Corr BM: Removal of Long Straight Sections | 12 d | 8/6/07 | 8/21/07 | 0% |
| 584 | Corrector Long (Verticle - Phase 1) Straight Spool Piece Assy, CLS | 324 d | 10/2/06 | 1/18/08 | 0% |
| 585 | Vert Corr CLS: Component Inspection & Cleaning | 3 d | 10/2/06 | 10/4/06 | 0% |
| 586 | Vert Corr CLS: Spool Piece Welding & Assy Upstairs | 9 d | 10/5/06 | 10/17/06 | 0% |
| 587 | Vert Corr CLS: Spool Piece Leak Checking | 9 d | 10/19/06 | 10/31/06 | 0% |
| 588 | Vert Corr CLS: Spool Piece Assy in Booster Enclosure | 6 d | 8/24/07 | 8/31/07 | 0% |
| 589 | Vert Corr CLS: Corrector Cooling Water Connection | 6 d | 11/2/07 | 11/9/07 | 0% |
| 590 | Vert Corr CLS: Spool Piece Cabling | 6 d | 11/12/07 | 11/19/07 | 0% |
| 591 | Vert Corr CLS: Spool Piece Power Testing | 6 d | 11/20/07 | 11/27/07 | 0% |
| 592 | Vert Corr CLS: Corrector & BPM Alignment | 6 d | 11/28/07 | 12/7/07 | 0% |
| 700 | Vertical Corrector Installation Complete | 0 d | 1/18/08 | 1/18/08 | 0% |
| 593 | Cooling Water Plumbing, LCW | 326 d | 7/19/06 | 11/1/07 | 0% |
| 594 | Vert Corr LCW: Water Circuit Design | 20 d | 7/19/06 | 8/15/06 | 0% |
| 595 | Vert Corr LCW: Procurement of Materials, Phase 1 All w/Long | 1 d | 9/27/06 | 9/27/06 | 0% |
| 596 | Vert Corr LCW: Tee in to Existing Header ( Phase 1) All w/Long | 7 d | 9/28/06 | 10/6/06 | 0% |
| 597 | Vert Corr LCW: Procurement of Materials, Phase 2 | 1 d | 9/28/06 | 9/28/06 | 0% |
| 598 | Vert Corr LCW: Build Sub-Headers & Leads, Phase 2 | 24 d | 10/1/07 | 11/1/07 | 0% |
| 758 | Vert Corr Applications Software Development | 376 d | 7/19/06 | 1/18/08 | 0% |
| 759 | Vert Corr Appl SW Dev: Specifications | 63 d | 7/19/06 | 10/16/06 | 0% |
| 761 | Vert Corr Appl SW Dev: Crate Level DAQ Software Development | 63 d | 10/17/06 | 1/22/07 | 0% |
| 760 | Vert Corr Appl SW Dev: Application Programming | 250 d | 1/23/07 | 1/18/08 | 0% |
| 687 | Horiz Corr Magnets Production | 270 d | 7/6/06 | 8/1/07 | 0% |
| 688 | Horiz Corr Magnets Design & Procurement | 236 d | 7/19/06 | 6/26/07 | 0% |
| 689 | Design Horiz Corr Production Units (24) | 10 d | 7/19/06 | 8/1/06 | 0% |
| 690 | Procure Horiz Corr Components | 226 d | 8/2/06 | 6/26/07 | 0% |
| 693 | Horiz Corr Magnets Fab & Test | 270 d | 7/6/06 | 8/1/07 | 0% |
| 694 | Fabricate Horiz Corr Production Units (24) | 149 d | 12/13/06 | 7/18/07 | 0% |
| 695 | Test Horiz Corr Production Units | 270 d | 7/6/06 | 8/1/07 | 0% |
| 696 | Horiz Corr Integrated BPMs | 140 d | 12/13/06 | 7/5/07 | 0% |
| 697 | Horiz Corr Magnets Ready for Installation | 0 d | 8/1/07 | 8/1/07 | 0% |
| 599 | Horizontal Corrector PS Fabrication | 209 d | 4/27/06 | 2/27/07 | 0% |
| 600 | Horiz Corr PS Production -- 50 Amp, PS1 | 158 d | 7/11/06 | 2/27/07 | 0% |
| 601 | Horiz Corr PS1: Production Specification & Vendor Selection | 10 d | 7/11/06 | 7/24/06 | 0% |
| 602 | Horiz Corr PS1: Production Oversight | 100 d | 7/25/06 | 12/14/06 | 0% |
| 749 | Horiz Corr PS1: Procurement Awarded | 1 d | 7/25/06 | 7/25/06 | 0% |
| 603 | Horiz Corr PS1: Production Order Fabrication, 120 Units | 48 d | 9/21/06 | 11/29/06 | 0% |
| 604 | Horiz Corr PS1: Production Order Testing | 48 d | 12/15/06 | 2/27/07 | 0% |
| 605 | Horiz Corr PS Production -- 5 Amp, PS2 | 25 d | 4/27/06 | 6/1/06 | 0% |
| 606 | Horiz Corr PS2: Production Order Fabrication, 24 Units | 1 d | 4/27/06 | 4/27/06 | 0% |
| 607 | Horiz Corr PS2: Production Order Testing | 24 d | 4/28/06 | 6/1/06 | 0% |
| 608 | Horizontal Corrector Installation | 494 d | 2/1/06 | 1/18/08 | 0% |
| 609 | Horiz Corr PS & Controls Rack Assembly | 390 d | 2/1/06 | 8/16/07 | 0% |
| 610 | CAMAC Horiz Corr Controller, CC | 75 d | 5/8/06 | 8/22/06 | 0% |
| 611 | Horiz Corr CC: Production Parts Procurement, 36 Units | 1 d | 6/19/06 | 6/19/06 | 0% |
| 612 | Horiz Corr CC: Production PCB Layout | 10 d | 5/8/06 | 5/19/06 | 0% |
| 613 | Horiz Corr CC: Production PCB Fabrication, 36 Units | 1 d | 6/19/06 | 6/19/06 | 0% |
| 614 | Horiz Corr CC: Production Assembly, 36 Units | 40 d | 6/20/06 | 8/15/06 | 0% |
| 615 | Horiz Corr CC: Production Testing | 40 d | 6/27/06 | 8/22/06 | 0% |
| 616 | Horiz Corr Local Displays & Diagnostics, DD | 59 d | 9/18/06 | 12/11/06 | 0% |
| 617 | Horiz Corr DD: Production Parts Procurement, 36 units | 1 d | 10/31/06 | 10/31/06 | 0% |
| 618 | Horiz Corr DD: Production PCB Layout | 5 d | 9/20/06 | 9/26/06 | 0% |
| 619 | Horiz Corr DD: Production PCB Fabrication, 36 Units | 1 d | 10/17/06 | 10/17/06 | 0% |
| 620 | Horiz Corr DD: Production Assembly, 36 Units | 9 d | 11/1/06 | 11/13/06 | 0% |
| 621 | Horiz Corr DD: Production Testing | 18 d | 11/14/06 | 12/11/06 | 0% |
| 622 | Horiz Corr DD: Documentation | 20 d | 9/18/06 | 10/13/06 | 0% |
| 623 | Horiz Corr Rack Installation, RI | 390 d | 2/1/06 | 8/16/07 | 0% |
| 624 | Horiz Corr RI: Identify New Rack Locations | 2 d | 7/19/06 | 7/20/06 | 0% |
| 625 | Horiz Corr RI: Specify Rack Layout & Cooling | 10 d | 7/21/06 | 8/3/06 | 0% |
| 626 | Horiz Corr RI: Create Drawings for Rack Layout | 5 d | 8/4/06 | 8/10/06 | 0% |
| 627 | Horiz Corr RI: Prepare New Rack Locations | 5 d | 2/1/06 | 2/7/06 | 0% |
| 628 | Horiz Corr RI: Transport Racks from Storage | 5 d | 2/8/06 | 2/14/06 | 0% |
| 629 | Horiz Corr RI: Prepare Racks with Equip. Support Hardware | 5 d | 2/15/06 | 2/21/06 | 0% |
| 630 | Horiz Corr RI: AC Power Installation | 21 d | 2/22/06 | 3/22/06 | 0% |
| 631 | Horiz Corr RI: Install Rack Cooling | 5 d | 3/23/06 | 3/29/06 | 0% |
| 632 | Horiz Corr RI: Install Bulk Power Supplies, 6 each 15kW Units | 5 d | 3/23/06 | 3/29/06 | 0% |
| 633 | Horiz Corr RI: Install Power Amplifiers | 10 d | 2/28/07 | 3/13/07 | 0% |
| 634 | Horiz Corr RI: Install Controls & Diagnostic Equip. | 40 d | 3/14/07 | 5/8/07 | 0% |
| 635 | Horiz Corr RI: Power Amplifier Test Design & Hazard Analysis | 10 d | 8/11/06 | 8/24/06 | 0% |
| 636 | Horiz Corr RI: Test Interlocks | 10 d | 5/9/07 | 5/22/07 | 0% |
| 637 | Horiz Corr RI: Test Power Amplifiers w/Load | 40 d | 5/23/07 | 7/19/07 | 0% |
| 638 | Horiz Corr RI: Test Controls | 20 d | 7/20/07 | 8/16/07 | 0% |
| 639 | Horiz Corr Cabling, CBL | 95 d | 7/11/06 | 11/21/06 | 0% |
| 640 | Horiz Corr CBL: Specify Power Cables & Connectors | 4 d | 7/11/06 | 7/14/06 | 0% |
| 641 | Horiz Corr CBL: Bid & Procure Power Cables | 1 d | 9/25/06 | 9/25/06 | 0% |
| 642 | Horiz Corr CBL: Procure Power Cable Connectors | 1 d | 11/6/06 | 11/6/06 | 0% |
| 643 | Horiz Corr CBL: Power Cable is Delivered | 1 d | 11/7/06 | 11/7/06 | 0% |
| 644 | Horiz Corr CBL: Pull Power Cables from Racks to Magnets | 10 d | 11/8/06 | 11/21/06 | 0% |
| 645 | Horiz Corr CBL: Specifying Control Cables & Connectors | 8 d | 7/11/06 | 7/20/06 | 0% |
| 646 | Horiz Corr CBL: Procure Control Cable & Connectors | 1 d | 8/31/06 | 8/31/06 | 0% |
| 647 | Horiz Corr CBL: Routing Control Cables | 4 d | 9/1/06 | 9/7/06 | 0% |
| 648 | Horiz Corr CBL: Terminating Control Cables | 40 d | 9/8/06 | 11/2/06 | 0% |
| 649 | Horiz Corrector Magnet Installation | 395 d | 6/21/06 | 1/18/08 | 0% |
| 650 | Horiz Corr Booster Modification, BM | 294 d | 6/21/06 | 8/21/07 | 0% |
| 651 | Horiz Corr BM: Design of New Short Straight Support | 10 d | 7/6/06 | 7/19/06 | 0% |
| 653 | Horiz Corr BM: Design of New SS Spool Piece | 10 d | 6/21/06 | 7/5/06 | 0% |
| 754 | Horiz Corr BM: Procure & Machining of Initial SS Spool Piece | 1 d | 9/14/06 | 9/14/06 | 0% |
| 755 | Horiz Corr BM: Assembly of Initial SS Spool Piece | 4 d | 9/15/06 | 9/20/06 | 0% |
| 756 | Horiz Corr BM: SS Initial Spool Piece Examination in Booster Enclosure | 6 d | 9/21/06 | 9/28/06 | 0% |
| 757 | Horiz Corr BM: Develop Drawings for Short Straight | 10 d | 9/29/06 | 10/12/06 | 0% |
| 652 | Horiz Corr BM: Procurement & Machining of SS Support | 1 d | 12/11/06 | 12/11/06 | 0% |
| 654 | Horiz Corr BM: Procure & Machining of SS Spool Piece Components | 1 d | 12/11/06 | 12/11/06 | 0% |
| 657 | Horiz Corr BM: Enclosure Installation Hazard Analysis | 12 d | 7/20/06 | 8/4/06 | 0% |
| 658 | Horiz Corr BM: Enclosure Work Safety Review | 2 d | 8/7/06 | 8/8/06 | 0% |
| 660 | Horiz Corr BM: Removal of Short Straight Sections | 12 d | 8/6/07 | 8/21/07 | 0% |
| 662 | Corrector Short (Horizontal - Phase 2) Straight Spool Piece Assy, CSS | 375 d | 7/20/06 | 1/18/08 | 0% |
| 663 | Horiz Corr CSS: Assembly & Installation Planning & Hazard Analysis | 5 d | 7/20/06 | 7/26/06 | 0% |
| 664 | Horiz Corr CSS: Component Inspection & Cleaning | 3 d | 12/12/06 | 12/14/06 | 0% |
| 665 | Horiz Corr CSS: Spool Piece Welding & Assy Upstairs | 6 d | 12/15/06 | 12/26/06 | 0% |
| 666 | Horiz Corr CSS: Spool Piece Leak Checking | 6 d | 12/18/06 | 12/27/06 | 0% |
| 667 | Horiz Corr CSS: Spool Piece Assy in Booster Enclosure | 6 d | 8/24/07 | 8/31/07 | 0% |
| 668 | Horiz Corr CSS: Corrector Cooling Water Connection | 6 d | 11/2/07 | 11/9/07 | 0% |
| 669 | Horiz Corr CSS: Spool Piece Cabling | 6 d | 11/12/07 | 11/19/07 | 0% |
| 670 | Horiz Corr CSS: Spool Piece Power Testing | 6 d | 11/20/07 | 11/27/07 | 0% |
| 671 | Horiz Corr CSS: Corrector & BPM Alignment | 6 d | 11/28/07 | 12/7/07 | 0% |
| 699 | Horizontal Correctors Installation Complete | 0 d | 1/18/08 | 1/18/08 | 0% |
| 681 | Horiz Corr Cooling Water Plumbing, LCW | 326 d | 7/19/06 | 11/1/07 | 0% |
| 682 | Horiz Corr LCW: Water Circuit Design | 20 d | 7/19/06 | 8/15/06 | 0% |
| 685 | Horiz Corr LCW: Procurement of Materials, Phase 2 Split betw Long & Short | 1 d | 9/27/06 | 9/27/06 | 0% |
| 686 | Horiz Corr LCW: Build Sub-Headers & Leads (Phase 2) Split betw Long & Short | 24 d | 10/1/07 | 11/1/07 | 0% |
| 764 | Horiz Corr Applications Software Development | 376 d | 7/19/06 | 1/18/08 | 0% |
| 765 | Horiz Corr Appl SW Dev: Specifications | 63 d | 7/19/06 | 10/16/06 | 0% |
| 766 | Horiz Corr Appl SW Dev: Crate Level DAQ Software Development | 63 d | 10/17/06 | 1/22/07 | 0% |
| 767 | Horiz Corr Appl SW Dev: Application Programming | 250 d | 1/23/07 | 1/18/08 | 0% |
| 768 | Commission Corrector System | 125 d | 1/22/08 | 7/16/08 | 0% |
| 801 | Corrector System Complete | 0 d | 7/16/08 | 7/16/08 | 0% |
| 769 | Vert Corr AIP Project Management | 376 d | 7/19/06 | 1/18/08 | 0% |
| 770 | Horiz Corr AIP Project Management | 376 d | 7/19/06 | 1/18/08 | 0% |
| 762 | Prepare AIP Documentation | 172 d | 8/1/05 | 4/7/06 | 0% |
| 784 | Corrector System Technical Review | 1 d | 7/18/06 | 7/18/06 | 0% |
| 763 | Corrector AIPs Approved | 0 d | 7/18/06 | 7/18/06 | 0% |
| 729 | Review Booster Modifications Design | 1 d | 7/20/06 | 7/20/06 | 0% |
| 785 | Corrector System Installation Review | 1 d | 3/1/07 | 3/1/07 | 0% |
| 728 | Corrector Magnets Spares Account (12 spares) | 130 d | 9/16/05 | 3/27/06 | 0% |
| 12 | 30 Hz Harmonic | 432 d | 1/3/05 | 9/18/06 | 34% |
| 279 | 30 Hz Harmonic Prototype | 412 d | 1/3/05 | 8/18/06 | 44% |
| 234 | GMPS Modification | 10 d | 8/7/06 | 8/18/06 | 0% |
| 214 | 30 Hz Harmonic Prototype | 232 d | 1/3/05 | 11/30/05 | 60% |
| 426 | Review 30 Hz Harmonic Prototype | 1 d | 12/1/05 | 12/1/05 | 0% |
| 233 | 30 Hz Harmonic Project Decision | 0 d | 12/1/05 | 12/1/05 | 0% |
| 230 | 30Hz Girder Design | 114 d | 6/21/05 | 12/1/05 | 15% |
| 280 | 30 Hz Harmonic Production | 199 d | 12/2/05 | 9/18/06 | 0% |
| 232 | 30Hz Procurement | 75 d | 12/2/05 | 3/23/06 | 0% |
| 333 | 30Hz Delivery | 1 d | 8/1/06 | 8/1/06 | 0% |
| 231 | 30Hz Installation | 30 d | 8/7/06 | 9/18/06 | 0% |
| 316 | 30Hz Installation Complete | 0 d | 9/18/06 | 9/18/06 | 0% |
| 13 | Gamma-t System | 681 d | 5/2/05 | 1/18/08 | 12% |
| 432 | Gamma-t System Studies | 168 d | 5/2/05 | 1/3/06 | 25% |
| 215 | Gamma-t Studies | 167 d | 5/2/05 | 12/29/05 | 25% |
| 408 | Gamma-t Studies Complete | 0 d | 12/29/05 | 12/29/05 | 0% |
| 431 | Gamma-t Review/Project Decision | 1 d | 1/3/06 | 1/3/06 | 0% |
| 433 | New Gamma-t System | 513 d | 1/4/06 | 1/18/08 | 0% |
| 434 | New Gamma-t System Design | 42 d | 1/4/06 | 3/3/06 | 0% |
| 435 | New Gamma-t System Procure/Fab | 125 d | 3/6/06 | 8/29/06 | 0% |
| 436 | New Gamma-t System Install | 21 d | 12/17/07 | 1/18/08 | 0% |
| 15 | Booster RF Cavity Cooling | 220 d | 1/4/05 | 11/11/05 | 80% |
| 157 | Stainless Steel Flex Tubes | 220 d | 1/4/05 | 11/11/05 | 80% |
| 155 | Flex Tube Fab | 39 d | 1/4/05 | 2/28/05 | 100% |
| 158 | Re-Install Flex Tubes | 10 d | 10/31/05 | 11/11/05 | 0% |
| 410 | Flex Tube Installation Complete | 0 d | 11/11/05 | 11/11/05 | 0% |
| 782 | Booster Solid State RF Upgrade | 1 d | 10/3/05 | 10/3/05 | 0% |
| 284 | Booster Dump Relocation | 173 d | 5/2/05 | 1/10/06 | 35% |
| 286 | Booster Dump Relocation Design | 86 d | 5/2/05 | 8/31/05 | 80% |
| 427 | Review Booster Dump Relocation Design | 1 d | 7/5/05 | 7/5/05 | 100% |
| 288 | Misc Fabrication | 10 d | 8/1/05 | 8/12/05 | 0% |
| 287 | Booster Dump Relocation Install | 163 d | 5/16/05 | 1/10/06 | 26% |
| 730 | Booster Dump Relocation Remove Shielding Wall | 8 d | 10/31/05 | 11/9/05 | 0% |
| 289 | Booster Dump Relocation Remove Existing MP01 Septum | 1 d | 11/30/05 | 11/30/05 | 0% |
| 290 | Booster Dump Relocation Install Replacement MP01 (Old MI-8) Septum | 5 d | 10/31/05 | 11/4/05 | 0% |
| 383 | Booster Dump Relocation Run Power to MP01 Septum | 150 d | 6/1/05 | 1/6/06 | 20% |
| 384 | Booster Dump Relocation Run Cooling Water to MP01 | 10 d | 10/31/05 | 11/11/05 | 0% |
| 291 | Booster Dump Relocation Remove Booster Kickers | 1 d | 11/7/05 | 11/7/05 | 0% |
| 292 | Booster Dump Relocation Install Booster Kickers | 5 d | 11/8/05 | 11/14/05 | 0% |
| 293 | Booster Dump Relocation Relocate Power Supplies | 10 d | 10/31/05 | 11/11/05 | 0% |
| 369 | Booster Dump Relocation Remove Beam Pipe @Conduit Core Location | 1 d | 10/31/05 | 10/31/05 | 0% |
| 803 | Booster Dump Relocation Issue Request for Proposals on Conduit Construction | 20 d | 7/1/05 | 7/29/05 | 100% |
| 294 | Booster Dump Relocation Install Conduit | 15 d | 11/1/05 | 11/21/05 | 0% |
| 368 | Booster Dump Relocation Terminate/Splice Cables/Controls | 3 d | 11/22/05 | 11/28/05 | 0% |
| 295 | Booster Dump Relocation Install Dump | 2 d | 10/31/05 | 11/1/05 | 0% |
| 296 | Booster Dump Relocation Radiation Safety Modifications | 149 d | 5/16/05 | 12/15/05 | 32% |
| 418 | Booster Dump Relocation Install Dump Switch for V803 | 22 d | 10/31/05 | 12/1/05 | 0% |
| 419 | Booster Dump Relocation Pull Cables for V803 | 10 d | 12/2/05 | 12/15/05 | 0% |
| 788 | Booster Dump Relocation Installation of Beam Dump | 3 d | 10/31/05 | 11/2/05 | 0% |
| 420 | Booster Dump Relocation Beam Stop Design/Fabrication | 97 d | 5/16/05 | 9/30/05 | 50% |
| 421 | Booster Dump Relocation Install Beam Stop | 10 d | 10/31/05 | 11/11/05 | 0% |
| 422 | Booster Dump Relocation Recable Interlock Chassis & Test | 10 d | 10/31/05 | 11/11/05 | 0% |
| 297 | Booster Dump Relocation Alignment | 2 d | 1/9/06 | 1/10/06 | 0% |
| 322 | Booster Dump Relocation Installation Complete | 0 d | 1/10/06 | 1/10/06 | 0% |
| 285 | Booster Chopper | 251 d | 10/3/05 | 10/2/06 | 0% |
| 372 | Specify Booster Chopper | 42 d | 10/3/05 | 12/1/05 | 0% |
| 797 | Booster Chopper Device | 183 d | 12/2/05 | 8/24/06 | 0% |
| 792 | Design Booster Chopper Magnet | 63 d | 12/5/05 | 3/8/06 | 0% |
| 428 | Review Booster Chopper | 1 d | 12/2/05 | 12/2/05 | 0% |
| 373 | Booster Chopper Procurement | 55 d | 3/9/06 | 5/24/06 | 0% |
| 374 | Booster Chopper Material Delivery | 1 d | 5/25/06 | 5/25/06 | 0% |
| 375 | Fab Booster Chopper | 63 d | 5/26/06 | 8/24/06 | 0% |
| 793 | Booster Chopper PS | 125 d | 12/2/05 | 6/2/06 | 0% |
| 794 | Booster Chopper PS Design | 42 d | 12/2/05 | 2/6/06 | 0% |
| 795 | Booster Chopper PS Procure | 63 d | 2/7/06 | 5/4/06 | 0% |
| 796 | Booster Chopper PS Assemble | 21 d | 5/4/06 | 6/2/06 | 0% |
| 376 | Test Booster Chopper w/Power Supply | 21 d | 8/25/06 | 9/25/06 | 0% |
| 377 | Booster Chopper Installation | 231 d | 10/31/05 | 10/2/06 | 0% |
| 370 | Remove Pinger Kickers (2) at Long 5 | 1 d | 10/31/05 | 10/31/05 | 0% |
| 371 | Install Booster Chopper | 2 d | 9/26/06 | 9/27/06 | 0% |
| 798 | Install Power Supply | 2 d | 6/5/06 | 6/6/06 | 0% |
| 378 | Electrical Hook-up | 1 d | 9/28/06 | 9/28/06 | 0% |
| 379 | Alignment | 1 d | 9/29/06 | 9/29/06 | 0% |
| 380 | Vacuum Pump Down | 1 d | 10/2/06 | 10/2/06 | 0% |
| 381 | Booster Chopper Installed | 0 d | 10/2/06 | 10/2/06 | 0% |
| 438 | Booster RF Reliability Improvements | 280 d | 8/22/05 | 10/2/06 | 0% |
| 731 | Booster AC Pulsed Power Transformer Replacement | 280 d | 8/22/05 | 10/2/06 | 0% |
| 439 | Booster AC Pulsed Power Transformer Purchase (3) | 125 d | 8/22/05 | 2/22/06 | 0% |
| 440 | Booster AC Pulsed Power Cabinet & Switchboard Purchase (2) | 85 d | 10/18/05 | 2/22/06 | 0% |
| 441 | New Transformers & Dist Cabinets (2) | 272 d | 9/1/05 | 10/2/06 | 0% |
| 743 | Design New Pads w/Containment | 63 d | 9/1/05 | 12/1/05 | 0% |
| 745 | Remove Old Transformers & Switchboards | 6 d | 8/7/06 | 8/14/06 | 0% |
| 744 | Civil Construction of New Pads & Containment | 30 d | 8/7/06 | 9/18/06 | 0% |
| 746 | Install New Transformers & Switchboards | 15 d | 9/12/06 | 10/2/06 | 0% |
| 802 | Booster AC Pulsed Transformer Installation Complete | 0 d | 10/2/06 | 10/2/06 | 0% |
| 747 | Booster RF Equip Upgrades to Improve Reliability | 1 d | 8/7/06 | 8/7/06 | 0% |
| 4 | Main Injector Upgrades | 568 d | 9/30/04 | 1/9/07 | 43% |
| 19 | Large Aperture Quads - WQB | 478 d | 9/30/04 | 8/25/06 | 61% |
| 204 | WQB Fabrication | 345 d | 9/30/04 | 2/17/06 | 73% |
| 203 | WQB TD Division FY04 Costs | 1 d | 9/30/04 | 9/30/04 | 100% |
| 86 | WQB Design | 218 d | 10/1/04 | 8/15/05 | 98% |
| 411 | WQB Design Complete | 0 d | 8/15/05 | 8/15/05 | 0% |
| 90 | WQB Procurement | 282 d | 10/11/04 | 11/22/05 | 98% |
| 92 | Procure WQB Tools | 172 d | 10/11/04 | 6/17/05 | 100% |
| 91 | Procure WQB Components | 143 d | 2/1/05 | 8/22/05 | 99% |
| 336 | WQB Components Delivery | 158 d | 4/12/05 | 11/22/05 | 95% |
| 94 | WQB Production | 256 d | 2/3/05 | 2/9/06 | 52% |
| 95 | WQB Produce Unit 1 | 142 d | 2/3/05 | 8/23/05 | 97% |
| 96 | WQB Produce Units 2 - 7 | 125 d | 4/28/05 | 10/24/05 | 46% |
| 135 | WQB Produce Units 8-9 (Spares) | 111 d | 8/29/05 | 2/9/06 | 0% |
| 97 | WQB Test | 130 d | 8/10/05 | 2/17/06 | 0% |
| 98 | WQB Test Unit 1 | 5 d | 9/9/05 | 9/15/05 | 0% |
| 99 | WQB Test Units 2 - 7 | 60 d | 8/10/05 | 11/2/05 | 0% |
| 136 | WQB Test Units 8-9 (Spares) | 65 d | 11/10/05 | 2/17/06 | 0% |
| 412 | WQB Ready for Installation | 0 d | 11/2/05 | 11/2/05 | 0% |
| 104 | WQB Install (AD) | 341 d | 4/20/05 | 8/25/06 | 5% |
| 106 | WQB Align/Install (5 units) | 30 d | 11/3/05 | 12/16/05 | 0% |
| 704 | WQB Align/Install (Remaining 2 units) | 15 d | 8/7/06 | 8/25/06 | 0% |
| 283 | WQB Misc Fabrication | 42 d | 8/31/05 | 10/28/05 | 0% |
| 324 | WQB Align/Install Complete | 0 d | 12/16/05 | 12/16/05 | 0% |
| 430 | Procure WQB BPM's Incl Cables & Cable Pulls | 94 d | 4/20/05 | 8/31/05 | 15% |
| 772 | Shutdown Preparation | 78 d | 8/1/05 | 11/17/05 | 0% |
| 206 | WQB Power Supplies | 160 d | 5/2/05 | 12/16/05 | 62% |
| 207 | WQB P.S. Procurement | 63 d | 5/2/05 | 7/29/05 | 100% |
| 208 | WQB P.S. Fab | 65 d | 6/30/05 | 9/30/05 | 50% |
| 210 | WQB P.S. Testing | 10 d | 10/3/05 | 10/14/05 | 0% |
| 413 | WQB P.S. Ready for Installation | 0 d | 10/14/05 | 10/14/05 | 0% |
| 209 | WQB P.S. Install | 15 d | 10/31/05 | 11/18/05 | 0% |
| 325 | WQB P.S. Installation Complete | 0 d | 11/18/05 | 11/18/05 | 0% |
| 414 | WQBs System Installed | 0 d | 12/16/05 | 12/16/05 | 0% |
| 20 | Collimation Systems | 464 d | 2/1/05 | 12/1/06 | 35% |
| 218 | Collimation Systems Design | 464 d | 2/1/05 | 12/1/06 | 46% |
| 107 | MI Loss Studies | 231 d | 2/1/05 | 12/29/05 | 49% |
| 113 | MI Loss Studies: Beam | 191 d | 2/1/05 | 10/28/05 | 50% |
| 110 | MI Loss Studies: Simulation | 204 d | 3/10/05 | 12/29/05 | 42% |
| 115 | MI Loss Study: Simulation | 167 d | 5/2/05 | 12/29/05 | 20% |
| 131 | MI-8 Loss Study: Simulation | 111 d | 3/10/05 | 8/15/05 | 75% |
| 109 | Exploratory Residual Radiation Measurements | 63 d | 2/1/05 | 4/28/05 | 100% |
| 134 | Systematic Residual Radiation Measurements | 178 d | 4/15/05 | 12/29/05 | 40% |
| 111 | MI-8 Collimation System Design & Commission | 269 d | 2/15/05 | 3/10/06 | 60% |
| 117 | Develop Concept for MI-8 Collimation System | 79 d | 2/15/05 | 6/6/05 | 100% |
| 118 | Review Concept for MI-8 Collimation System | 1 d | 6/7/05 | 6/7/05 | 100% |
| 119 | Design MI-8 Collimation System | 60 d | 6/8/05 | 8/31/05 | 50% |
| 133 | MI-8 Collimation System Commissioning | 42 d | 1/11/06 | 3/10/06 | 0% |
| 112 | MI Collimation System Design & Commission | 233 d | 1/3/06 | 12/1/06 | 0% |
| 121 | Develop Concept for MI Collimation System | 21 d | 1/3/06 | 2/1/06 | 0% |
| 122 | Review Concept for MI Collimation System | 1 d | 2/2/06 | 2/2/06 | 0% |
| 123 | Design MI Collimation System | 42 d | 2/3/06 | 4/3/06 | 0% |
| 127 | MI Collimation System Commissioning | 42 d | 10/3/06 | 12/1/06 | 0% |
| 341 | MI-8 Collimation Syst Procure/Fab/Install | 108 d | 8/1/05 | 1/6/06 | 0% |
| 252 | Procure MI-8 Collimation System | 63 d | 8/1/05 | 10/27/05 | 0% |
| 251 | Fabricate MI-8 Collimation System | 63 d | 9/13/05 | 12/12/05 | 0% |
| 120 | Install MI-8 Collimators | 15 d | 12/13/05 | 1/6/06 | 0% |
| 326 | MI-8 Collimators Installation Complete | 0 d | 1/6/06 | 1/6/06 | 0% |
| 338 | MI Collimation Syst Procure/Fab/Install | 120 d | 4/4/06 | 9/21/06 | 0% |
| 253 | Procure MI Collimation System | 84 d | 4/4/06 | 8/1/06 | 0% |
| 124 | Fabricate MI Collimation System (Future Parent) | 63 d | 6/2/06 | 8/30/06 | 0% |
| 125 | Install/Align MI Collimation System | 15 d | 8/31/06 | 9/21/06 | 0% |
| 327 | MI Collimation System Install/Align Complete | 0 d | 9/21/06 | 9/21/06 | 0% |
| 126 | Main Injector Loss Mitigation Complete | 0 d | 12/1/06 | 12/1/06 | 0% |
| 21 | NuMI Multibatch Operation | 483 d | 2/7/05 | 1/9/07 | 21% |
| 219 | Multi-batch Studies | 483 d | 2/7/05 | 1/9/07 | 36% |
| 128 | Mixed Mode Operation (5) | 138 d | 2/18/05 | 9/1/05 | 40% |
| 129 | Studies for NuMI Slip Stacking | 125 d | 7/10/06 | 1/9/07 | 0% |
| 703 | Slip Stacking for NuMI Complete | 0 d | 1/9/07 | 1/9/07 | 0% |
| 130 | Barrier Bucket R&D | 358 d | 2/7/05 | 7/7/06 | 51% |
| 149 | Barrier Bucket Cavity | 197 d | 2/7/05 | 11/11/05 | 91% |
| 150 | Barrier Bucket Cavity Procurement | 80 d | 2/7/05 | 5/27/05 | 100% |
| 151 | Barrier Bucket Cavity Fabrication/Assembly | 67 d | 5/31/05 | 9/1/05 | 95% |
| 152 | Barrier Bucket Cavity Installation | 10 d | 10/31/05 | 11/11/05 | 0% |
| 328 | Barrier Bucket Cavity Installation Complete | 0 d | 11/11/05 | 11/11/05 | 0% |
| 153 | Barrier Bucket Commissioning | 125 d | 1/11/06 | 7/7/06 | 0% |
| 254 | Injection Kicker Modifications (Cooling System) | 133 d | 6/7/05 | 12/14/05 | 5% |
| 392 | Inj Kicker Mods Design/Drafting & Procurement | 98 d | 6/7/05 | 10/24/05 | 8% |
| 394 | Load Temperature Control System Design | 63 d | 6/7/05 | 9/2/05 | 5% |
| 393 | Load Resistor Design | 26 d | 7/29/05 | 9/2/05 | 25% |
| 395 | Procure Resistors & High Power Parts | 80 d | 7/1/05 | 10/24/05 | 5% |
| 396 | Procure Control Skid & Temperature Controls | 35 d | 7/18/05 | 9/2/05 | 5% |
| 402 | Inj Kicker Mods Assemble/Test | 55 d | 9/6/05 | 11/21/05 | 0% |
| 399 | Assemble/Test Control Skid | 38 d | 9/6/05 | 10/27/05 | 0% |
| 400 | Assemble/Test Resistors | 30 d | 10/11/05 | 11/21/05 | 0% |
| 726 | Injection Kicker Mod Ready for Installation | 0 d | 11/21/05 | 11/21/05 | 0% |
| 403 | Inj Kicker Mods Installation | 32 d | 10/28/05 | 12/14/05 | 0% |
| 397 | Install Control Skid in MI-10 incl Power | 5 d | 11/22/05 | 11/30/05 | 0% |
| 401 | Install Low Conductivity Water for Control Skid | 20 d | 10/28/05 | 11/28/05 | 0% |
| 398 | Install Resistors on Magnet & Plumbing from Svc Bldg in Tunnel | 15 d | 11/22/05 | 12/14/05 | 0% |
| 727 | Injection Kicker Mods Complete | 0 d | 11/30/05 | 11/30/05 | 0% |
| 255 | Extraction Kicker Modifications | 148 d | 11/1/05 | 6/6/06 | 0% |
| 22 | Main Injector RF Upgrade | 255 d | 3/1/05 | 3/6/06 | 53% |
| 263 | MI RF Upgrade Prototype | 119 d | 3/1/05 | 8/16/05 | 99% |
| 55 | Test MI RF Upgrade Prototype Cavity in MI | 119 d | 3/1/05 | 8/16/05 | 99% |
| 271 | High Intensity Beam Studies | 26 d | 7/5/05 | 8/9/05 | 100% |
| 52 | Upgrade MI RF Prototype Cavity | 116 d | 3/1/05 | 8/11/05 | 100% |
| 773 | MI RF Cavity Prototype Decision | 0 d | 8/16/05 | 8/16/05 | 0% |
| 774 | MI RF Upgrade | 125 d | 9/1/05 | 3/6/06 | 0% |
| 775 | MI RF Upgrade Study | 125 d | 9/1/05 | 3/6/06 | 0% |
| 776 | MI RF Scope Decision | 0 d | 3/6/06 | 3/6/06 | 0% |
| 5 | Management | 870 d | 2/1/05 | 7/16/08 | 16% |
| 220 | Management | 870 d | 2/1/05 | 7/16/08 | 16% |
| 406 | Management Reserve OP | 1 d | 10/3/05 | 10/3/05 | 0% |
| 407 | Management Reserve EQ | 1 d | 10/3/05 | 10/3/05 | 0% |
| 59 | Start 2005 Shutdown | |