| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 1 | Proton Plan | 1140 d | Thu 9/30/04 | Fri 4/17/09 | | 60% |
| 2 | Linac Upgrades | 656 d | Wed 12/15/04 | Fri 7/27/07 | | 44% |
| 3 | Linac PA Vulnerability | 471 d | Wed 12/15/04 | Mon 10/30/06 | | 94% |
| 4 | Linac PA Task Force | 471 d | Wed 12/15/04 | Mon 10/30/06 | | 89% |
| 5 | Linac Task Force: Phase 1 | 39 d | Wed 12/15/04 | Mon 2/14/05 | AD Electrical Engineer[3%],M&S[5,000] | 100% |
| 6 | Linac Task Force Phase 1 Report Issued | 0 d | Mon 2/14/05 | Mon 2/14/05 | | 100% |
| 7 | Linac Task Force: Phase 2 | 97 d | Tue 2/15/05 | Thu 6/30/05 | AD Project Manager[1%] | 100% |
| 8 | Linac Task Force Phase 2 Report Issued | 0 d | Thu 6/30/05 | Thu 6/30/05 | | 100% |
| 9 | Linac Task Force 2 | 230 d | Thu 12/1/05 | Mon 10/30/06 | AD Project Manager[27%],AD Physicist[11%],AD RF Electrical Engineer[11%],M&S[5,000] | 83% |
| 10 | Linac Task Force 2 Complete | 0 d | Mon 10/30/06 | Mon 10/30/06 | | 0% |
| 11 | 7835 Amplifier Tubes Spares | 272 d | Fri 2/18/05 | Mon 3/20/06 | | 100% |
| 12 | Linac Task Force PA Prepare Order | 21 d | Fri 2/18/05 | Fri 3/18/05 | AD Electrical Engineer[20%] | 100% |
| 13 | Linac Task Force PA Award & Delivery (9) | 251 d | Mon 3/21/05 | Mon 3/20/06 | M&S[1,406,565] | 100% |
| 14 | Thales Prototype Facility (Deleted in CR#18) | 22 d | Thu 6/1/06 | Fri 6/30/06 | | 100% |
| 15 | Thales Prototype Facility (Deleted in CR#18) | 22 d | Thu 6/1/06 | Fri 6/30/06 | | 100% |
| 16 | Rebuild Hydrogen Furnace | 1 d | Tue 1/3/06 | Tue 1/3/06 | M&S[57,435] | 100% |
| 17 | Linac Quad Power Supplies | 647 d | Mon 1/3/05 | Fri 7/27/07 | | 32% |
| 18 | Linac Quad PS: Design & Prototype | 149 d | Mon 1/3/05 | Tue 8/2/05 | | 100% |
| 19 | Linac Quad PS Conceptual Specifications | 148 d | Mon 1/3/05 | Mon 8/1/05 | AD Physicist[25%],AD Electrical Engineer[25%] | 100% |
| 20 | Linac Quad PS Conceptual 300 amp Test | 85 d | Fri 4/1/05 | Mon 8/1/05 | AD Electrical Engineer[13%],AD Electrical Technician[26%] | 100% |
| 21 | Linac Quad PS Conceptual Review Prototype | 1 d | Tue 8/2/05 | Tue 8/2/05 | | 100% |
| 22 | Linac Quad PS Conceptual Design | 87 d | Tue 3/1/05 | Thu 6/30/05 | AD Electrical Engineer[55%],M&S[2,000] | 100% |
| 23 | Linac Quad PS Conceptual Inductor Design | 87 d | Tue 3/1/05 | Thu 6/30/05 | AD Mechanical Engineer[14%] | 100% |
| 24 | Linac Quad PS Project Decision | 0 d | Mon 8/1/05 | Mon 8/1/05 | | 100% |
| 25 | Linac Quad PS Upgrade - Card Replacement | 456 d | Mon 10/3/05 | Fri 7/27/07 | | 12% |
| 26 | Linac Quad PS Upgrade Design | 310 d | Mon 10/3/05 | Thu 12/28/06 | AD Electrical Engineer[117%] | 25% |
| 27 | Linac Quad PS Card Replacement Design Review (Deleted in CR#11) | 1 d | Mon 4/24/06 | Mon 4/24/06 | | 100% |
| 28 | Linac Quad PS Upgrade Drafting | 270 d | Fri 2/3/06 | Thu 3/1/07 | AD Drafter/Designer[33%] | 13% |
| 29 | Linac Quad PS Upgrade Procurement | 290 d | Fri 3/3/06 | Thu 4/26/07 | AD Electrical Engineer[1%],M&S[110,000] | 13% |
| 30 | Linac Quad PS Upgrade Test | 291 d | Thu 6/1/06 | Fri 7/27/07 | AD Electrical Technician[14%],AD Electrical Engineer[21%] | 5% |
| 31 | Linac Quad PS Upgrade Install | 291 d | Thu 6/1/06 | Fri 7/27/07 | AD Electrical Technician[3%],AD Electrical Engineer[0%] | 5% |
| 32 | Linac Quad PS Upgrade Installation Complete | 0 d | Fri 7/27/07 | Fri 7/27/07 | | 0% |
| 33 | 200 Mhz LLRF Upgrade | 456 d | Mon 10/3/05 | Fri 7/27/07 | | 31% |
| 34 | 200 Mhz LLRF Engineering | 293 d | Mon 10/3/05 | Fri 12/1/06 | | 70% |
| 35 | 200 Mhz LLRF Modeling | 208 d | Mon 10/3/05 | Tue 8/1/06 | AD Electrical Engineer[66%],M&S[22,440] | 99% |
| 36 | 200 Mhz LLRF Engineering | 85 d | Wed 8/2/06 | Fri 12/1/06 | AD RF Electrical Engineer[162%],AD Computer Professional[294%],AD Drafter/Designer[294%],AD Electrical Engineer[44%] | 0% |
| 37 | 200 Mhz LLRF Design Review | 1 d | Fri 12/1/06 | Fri 12/1/06 | AD Physicist[200%],AD Electrical Engineer | 0% |
| 38 | 200 Mhz LLRF Procure/Assy/Test/Install | 165 d | Wed 11/1/06 | Fri 6/29/07 | | 0% |
| 39 | 200 Mhz LLRF Procurement | 84 d | Mon 12/4/06 | Thu 4/5/07 | AD RF Electrical Engineer[2%],M&S[125,000] | 0% |
| 40 | 200 Mhz LLRF Assembly | 125 d | Wed 11/1/06 | Thu 5/3/07 | AD RF Tech[200%],AD RF Electrical Engineer[10%] | 0% |
| 41 | 200 Mhz LLRF Testing | 125 d | Fri 12/1/06 | Fri 6/1/07 | AD RF Tech[40%],AD Electrical Engineer[20%] | 0% |
| 42 | 200 Mhz LLRF Installation | 20 d | Mon 6/4/07 | Fri 6/29/07 | AD RF Tech[210%],AD Electrical Technician[210%] | 0% |
| 43 | 200 Mhz LLRF Commissioning | 19 d | Mon 7/2/07 | Fri 7/27/07 | AD RF Electrical Engineer[105%],AD RF Tech[211%] | 0% |
| 44 | 200 Mhz LLRF Installation Complete | 0 d | Fri 7/27/07 | Fri 7/27/07 | | 0% |
| 45 | Booster Upgrades | 1140 d | Thu 9/30/04 | Fri 4/17/09 | | 55% |
| 46 | Booster RF Duty Cycle Limits & Means of Improving Booster RF Reliability for 9Hz Operation | 242 d | Mon 8/22/05 | Tue 8/8/06 | | 86% |
| 47 | Feasibility of Booster RF Operating @ 9Hz | 242 d | Mon 8/22/05 | Tue 8/8/06 | | 76% |
| 48 | Determine Duty Cycle Limit for Booster West Gallery Transformer (Y02-US-01) | 5 d | Mon 8/22/05 | Fri 8/26/05 | AD Electrical Engineer[60%] | 100% |
| 49 | Investigate Reprogramming Ferrite Bias Program to Reduce RMS Current | 162 d | Tue 9/6/05 | Fri 4/28/06 | AD Physicist[13%],AD Electrical Engineer[5%] | 100% |
| 50 | Determine Duty Cycle Limit for Booster West Gallery Ferrite Bias Supply Transformers | 10 d | Tue 11/15/05 | Wed 11/30/05 | AD Electrical Engineer[20%],AD Electrical Technician[20%] | 100% |
| 51 | Review Duty Cycle Limit Study Results w/FESS Engineering Electrical Consultant | 18 d | Wed 10/5/05 | Fri 10/28/05 | AD Electrical Engineer[17%],M&S[800] | 100% |
| 52 | Document Findings & Recommendations w/Report | 173 d | Mon 11/21/05 | Tue 8/1/06 | AD Electrical Engineer[47%] | 50% |
| 53 | Booster RF Report Issued | 0 d | Tue 8/8/06 | Tue 8/8/06 | | 0% |
| 54 | Strategies for Improving Booster RF Reliability @ 9Hz | 224 d | Fri 9/9/05 | Tue 8/1/06 | | 97% |
| 55 | Review Station Down Time for Determining Equip Vulnerability | 116 d | Fri 9/9/05 | Tue 2/28/06 | AD Electrical Engineer[2%] | 100% |
| 56 | Develop Action Plan to Improve Reliability | 181 d | Wed 11/9/05 | Tue 8/1/06 | AD Electrical Engineer[2%] | 95% |
| 57 | OrBump System | 427 d | Thu 9/30/04 | Wed 6/14/06 | | 100% |
| 58 | OrBump System Magnets Design & Production | 380 d | Thu 9/30/04 | Fri 4/7/06 | | 100% |
| 59 | OrBump Magnet TD Division FY04 Costs | 1 d | Thu 9/30/04 | Thu 9/30/04 | TD Mechanical Engineer[12,650%],TD Mechanical Technician[5,575%] | 100% |
| 60 | OrBump Magnets | 330 d | Fri 10/1/04 | Tue 1/31/06 | | 100% |
| 61 | Design OrBump Magnets (3+3 spares) | 248 d | Fri 10/1/04 | Tue 9/27/05 | TD Mechanical Engineer[49%],TD Mechanical Technician[19%] | 100% |
| 62 | Procure Components & Tooling for OrBump Magnets (3+3 spares) | 165 d | Fri 2/4/05 | Tue 9/27/05 | TD Mechanical Engineer[37%],TD Mechanical Technician[37%] | 100% |
| 63 | Assemble, Test & Rework 1st Article OrBump Magnet | 272 d | Fri 10/1/04 | Mon 10/31/05 | TD Mechanical Engineer[12%],TD Mechanical Technician[56%] | 100% |
| 64 | Assemble Final 5 OrBump Magnets (2+3 spares) | 227 d | Wed 2/23/05 | Thu 1/19/06 | TD Mechanical Engineer[8%],TD Mechanical Technician[131%] | 100% |
| 65 | Test Final 5 OrBump Magnets (2+3 spares) (AD) | 48 d | Tue 11/1/05 | Fri 1/13/06 | AD Engineer[36%] | 100% |
| 66 | OrBump Magnets Ready for Install on Girder | 0 d | Tue 1/31/06 | Tue 1/31/06 | | 100% |
| 67 | OrBump Stripline | 229 d | Fri 4/1/05 | Wed 3/1/06 | | 100% |
| 68 | Design OrBump Stripline | 148 d | Fri 4/1/05 | Fri 10/28/05 | TD Mechanical Engineer[13%],TD Mechanical Technician[13%] | 100% |
| 69 | Procure OrBump Stripline | 76 d | Fri 9/9/05 | Thu 12/29/05 | TD Mechanical Technician[1%] | 100% |
| 70 | Assemble OrBump Stripline | 37 d | Mon 1/9/06 | Wed 3/1/06 | TD Mechanical Engineer[3%],TD Mechanical Technician[16%] | 100% |
| 71 | OrBump Stripline Assy Complete | 0 d | Wed 3/1/06 | Wed 3/1/06 | | 100% |
| 72 | OrBump Girder | 256 d | Fri 4/1/05 | Fri 4/7/06 | | 100% |
| 73 | Design OrBump Girder Assembly | 181 d | Fri 4/1/05 | Fri 12/16/05 | TD Mechanical Engineer[8%],TD Mechanical Technician[32%] | 100% |
| 74 | Procure OrBump Girder Assembly | 122 d | Fri 7/29/05 | Thu 1/26/06 | TD Mechanical Engineer[3%],TD Mechanical Technician[22%] | 100% |
| 75 | Mount OrBump Components on Girder | 51 d | Fri 1/27/06 | Fri 4/7/06 | TD Mechanical Engineer[15%],TD Mechanical Technician[89%] | 100% |
| 76 | Survey OrBump Magnets & Girder | 2 d | Wed 2/1/06 | Thu 2/2/06 | PPD Survey Engineer[250%],PPD Survey Technician[500%] | 100% |
| 77 | OrBump Girder Assy Complete | 0 d | Fri 4/7/06 | Fri 4/7/06 | | 100% |
| 78 | OrBump System Power Supply | 300 d | Tue 1/25/05 | Mon 4/3/06 | | 100% |
| 79 | OrBump P.S. Specifications | 5 d | Tue 1/25/05 | Mon 1/31/05 | AD Electrical Engineer[50%],AD Physicist[25%] | 100% |
| 80 | OrBump P.S. Simulations | 10 d | Tue 2/1/05 | Mon 2/14/05 | AD Electrical Engineer[50%] | 100% |
| 81 | OrBump P.S. Design Review Preparation | 21 d | Mon 5/9/05 | Tue 6/7/05 | AD Electrical Engineer | 100% |
| 82 | OrBump P.S. Design Review | 1 d | Wed 6/15/05 | Wed 6/15/05 | AD Electrical Engineer | 100% |
| 83 | OrBump P.S. Cabinet Layout | 118 d | Wed 6/1/05 | Tue 11/15/05 | AD Electrical Engineer[57%] | 100% |
| 84 | OrBump P.S. General Procurement | 275 d | Tue 3/1/05 | Mon 4/3/06 | AD Electrical Engineer[6%],M&S[101,000] | 100% |
| 85 | OrBump P.S. Procure Capacitors | 161 d | Tue 2/15/05 | Fri 9/30/05 | AD Electrical Engineer[4%],M&S[29,000] | 100% |
| 86 | OrBump Charging Power Supply Assembly | 143 d | Mon 4/11/05 | Mon 10/31/05 | AD Electrical Technician[158%],AD Electrical Engineer[24%] | 100% |
| 87 | OrBump P.S. Cabinet Assembly | 54 d | Wed 11/16/05 | Wed 2/8/06 | AD Electrical Technician[276%],AD Electrical Engineer[32%] | 100% |
| 88 | OrBump P.S. Assemble Controls | 198 d | Fri 6/17/05 | Mon 4/3/06 | AD Electrical Technician[38%],AD Electrical Engineer[6%] | 100% |
| 89 | OrBump P.S. Initial Testing | 35 d | Fri 1/27/06 | Thu 3/16/06 | AD Electrical Engineer[85%],AD Electrical Technician[85%] | 100% |
| 90 | OrBump Power Supply Ready for Installation | 0 d | Thu 3/16/06 | Thu 3/16/06 | | 100% |
| 91 | OrBump Syst Installation | 259 d | Mon 5/2/05 | Thu 5/11/06 | | 100% |
| 92 | Installation | 24 d | Mon 4/10/06 | Thu 5/11/06 | | 100% |
| 93 | Install OrBump Power Supply | 5 d | Mon 4/24/06 | Fri 4/28/06 | AD Electrical Technician[150%],AD Electrical Engineer[50%],M&S[6,400] | 100% |
| 94 | Install OrBump Magnet System | 8 d | Mon 4/10/06 | Wed 4/19/06 | AD Mechanical Technician[525%],AD Electrical Technician[200%],AD Mechanical Engineer[53%] | 100% |
| 95 | Pull Cables/Terminate/Install Head | 2 d | Mon 4/17/06 | Tue 4/18/06 | AD Electrical Technician[150%],AD Electrical Engineer[6%],M&S[2,000] | 100% |
| 96 | OrBump System Survey - AD | 7 d | Thu 4/20/06 | Fri 4/28/06 | AD Mechanical Technician[14%],AD Mechanical Engineer[2%] | 100% |
| 97 | OrBump System Survey - PPD | 7 d | Thu 4/20/06 | Fri 4/28/06 | PPD Survey Engineer[29%],PPD Survey Technician[86%] | 100% |
| 98 | OrBump System Installation Complete | 0 d | Thu 5/11/06 | Thu 5/11/06 | | 100% |
| 99 | 400 MEV Line Reconfiguration | 259 d | Mon 5/2/05 | Thu 5/11/06 | | 100% |
| 100 | 400 MeV Beamline Design | 107 d | Mon 5/2/05 | Fri 9/30/05 | | 100% |
| 101 | 400 MeV Optics Design | 21 d | Mon 5/2/05 | Tue 5/31/05 | AD Physicist | 100% |
| 102 | 400 MeV Beam Sheet | 2 d | Thu 7/14/05 | Fri 7/15/05 | AD Physicist | 100% |
| 103 | 400 MeV Drawing | 54 d | Mon 7/18/05 | Fri 9/30/05 | AD Physicist[13%],AD Mechanical Engineer[20%],AD Drafter/Designer[50%] | 100% |
| 104 | 400 MeV Alignment | 233 d | Wed 6/1/05 | Thu 5/4/06 | | 100% |
| 105 | 400 MeV Beam Sheet Based on As-found '04 | 30 d | Wed 6/1/05 | Wed 7/13/05 | PPD Survey Engineer[37%] | 100% |
| 106 | 400 MeV Delimiter New Stationing | 1 d | Wed 3/15/06 | Wed 3/15/06 | PPD Survey Technician[900%] | 100% |
| 107 | 400 MeV Survey - AD | 4 d | Mon 5/1/06 | Thu 5/4/06 | AD Mechanical Technician,AD Mechanical Engineer[9%] | 100% |
| 108 | 400 MeV Survey - PPD | 4 d | Mon 5/1/06 | Thu 5/4/06 | PPD Survey Technician[300%] | 100% |
| 109 | 400 MeV Installation | 49 d | Mon 3/6/06 | Thu 5/11/06 | | 100% |
| 110 | 400 MeV Vent Vacuum/Disconnect Electrical/LCW | 2 d | Mon 3/6/06 | Tue 3/7/06 | AD Mechanical Technician[400%],AD Mechanical Engineer[44%] | 100% |
| 111 | 400 MeV Remove Magnets & Other Components | 5 d | Wed 3/8/06 | Tue 3/14/06 | AD Electrical Technician[300%],AD Mechanical Technician[400%],AD Mechanical Engineer[40%] | 100% |
| 112 | 400 MeV Install Magnets & Other Components - AD | 5 d | Thu 4/20/06 | Wed 4/26/06 | AD Mechanical Technician[400%],AD Mechanical Engineer[40%] | 100% |
| 113 | 400 MeV Install Magnets & Other Components - PPD | 5 d | Thu 4/20/06 | Wed 4/26/06 | PPD Survey Engineer[10%],PPD Survey Technician[20%] | 100% |
| 114 | 400 MeV Connect Vacuum System/Pump Down/Leak Check | 3 d | Fri 5/5/06 | Tue 5/9/06 | AD Mechanical Technician[300%],AD Mechanical Engineer[29%] | 100% |
| 115 | 400 MeV Connect Water/Electrical | 2 d | Wed 5/10/06 | Thu 5/11/06 | AD Mechanical Technician[200%],AD Electrical Technician[300%],AD Mechanical Engineer[19%] | 100% |
| 116 | 400 MeV Electrical | 2 d | Fri 5/5/06 | Mon 5/8/06 | | 100% |
| 117 | 400 MeV Isolate MH2 Power Cables | 1 d | Fri 5/5/06 | Fri 5/5/06 | AD Electrical Technician | 100% |
| 118 | 400 MeV MH2 PS Change Gain | 1 d | Mon 5/8/06 | Mon 5/8/06 | AD Electrical Engineer[13%] | 100% |
| 119 | Commission OrBump System | 10 d | Thu 6/1/06 | Wed 6/14/06 | AD Physicist[200%] | 100% |
| 120 | OrBump System Commissioned | 0 d | Wed 6/14/06 | Wed 6/14/06 | | 100% |
| 121 | Corrector System | 1078 d | Tue 1/4/05 | Fri 4/17/09 | | 29% |
| 122 | Corrector Magnets Design & Prototype | 475 d | Tue 1/4/05 | Fri 11/17/06 | | 80% |
| 123 | Initial Corrector Prototype Design & Fab | 146 d | Tue 1/4/05 | Fri 7/29/05 | TD Mechanical Engineer[60%],TD Drafter/Designer[30%],M&S[15,000] | 100% |
| 124 | Design Corrector Prototype | 305 d | Tue 8/16/05 | Tue 10/31/06 | TD Mechanical Engineer[81%],TD Drafter/Designer[49%] | 82% |
| 125 | Corrector Prototype Procurement | 401 d | Tue 3/1/05 | Fri 9/29/06 | TD Mechanical Technician[16%],M&S[143,000] | 95% |
| 126 | Corrector Prototype Production | 391 d | Tue 4/12/05 | Fri 10/27/06 | TD Mechanical Engineer[11%],TD Drafter/Designer[2%],TD Mechanical Technician[108%],M&S[2,000] | 75% |
| 127 | Corrector Prototype Test | 108 d | Mon 6/19/06 | Fri 11/17/06 | TD Mechanical Engineer[6%] | 10% |
| 128 | Corrector Prototype Magnet Complete | 0 d | Fri 11/17/06 | Fri 11/17/06 | | 0% |
| 129 | Corr Prototype Design Complete | 0 d | Tue 10/31/06 | Tue 10/31/06 | | 0% |
| 130 | Long Straight BM: Prel Measurement of Long Straights | 10 d | Mon 4/10/06 | Fri 4/21/06 | AD Electrical Engineer[50%],AD Mechanical Engineer[50%] | 100% |
| 131 | Short Straight BM: Examination & Measurement of Short Straights | 10 d | Mon 4/3/06 | Fri 4/14/06 | AD Mechanical Engineer[50%],AD Electrical Engineer[50%] | 100% |
| 132 | Long Straight Magnets Production | 192 d | Tue 8/22/06 | Tue 5/29/07 | | 0% |
| 133 | Long Straight Magnets Design & Procurement | 180 d | Tue 8/22/06 | Thu 5/10/07 | | 0% |
| 134 | Design Long Straight Production Units (24) | 10 d | Mon 11/6/06 | Fri 11/17/06 | TD Mechanical Engineer[158%],TD Mechanical Technician[364%] | 0% |
| 135 | Procure Long Straight Components | 180 d | Tue 8/22/06 | Thu 5/10/07 | TD Mechanical Engineer[1%],TD Mechanical Technician[7%],M&S[679,707] | 0% |
| 136 | Long Straight Magnets Fab & Test | 92 d | Fri 1/19/07 | Tue 5/29/07 | | 0% |
| 137 | Fabricate Long Straight Production Units (24) | 90 d | Fri 1/19/07 | Thu 5/24/07 | TD Mechanical Engineer[233%],TD Mechanical Technician[717%] | 0% |
| 138 | Test Long Straight Production Units | 70 d | Tue 2/20/07 | Tue 5/29/07 | | 0% |
| 139 | Long Straight Integrated BPMs | 140 d | Tue 8/22/06 | Thu 3/15/07 | TD Mechanical Technician[32%],M&S[36,720] | 0% |
| 140 | Long Straight Magnets Ready for Installation | 0 d | Tue 5/29/07 | Tue 5/29/07 | | 0% |
| 141 | Corrector PS Design & Prototype | 326 d | Mon 8/1/05 | Tue 11/14/06 | | 84% |
| 142 | Magnet Power Supplies -- 50 Amp, PS1 | 263 d | Mon 8/1/05 | Wed 8/16/06 | | 96% |
| 143 | PS1: Specification | 20 d | Mon 8/1/05 | Fri 8/26/05 | AD Electrical Engineer[50%],AD Electrical Technician[50%] | 100% |
| 144 | PS1: Identify Vendors | 4 d | Mon 8/29/05 | Thu 9/1/05 | AD Electrical Engineer[50%],AD Electrical Technician[50%] | 100% |
| 145 | PS1: Vendor Specification Review | 20 d | Mon 8/1/05 | Fri 8/26/05 | AD Electrical Engineer[5%] | 100% |
| 146 | PS1: Request For Inquiry Bids | 4 d | Mon 8/29/05 | Thu 9/1/05 | AD Electrical Engineer[13%] | 100% |
| 147 | PS1: Procurement of Vendor Model | 1 d | Tue 12/27/05 | Tue 12/27/05 | AD Electrical Engineer[200%],M&S[4,500] | 100% |
| 148 | PS1: Prototype In-House PS Design | 115 d | Mon 9/19/05 | Tue 3/7/06 | AD Electrical Engineer[52%],AD Electrical Technician[52%] | 100% |
| 149 | PS1: Prototype Fabrication | 1 d | Tue 3/7/06 | Tue 3/7/06 | AD Electrical Engineer[50%],M&S[4,000] | 100% |
| 150 | PS1: Prototype Testing | 93 d | Mon 4/3/06 | Fri 8/11/06 | AD Electrical Engineer[50%],AD Electrical Technician[50%],M&S[2,000] | 90% |
| 151 | PS1: Approval For Production | 2 d | Tue 8/15/06 | Wed 8/16/06 | AD Electrical Engineer | 0% |
| 152 | Magnet Power Supplies -- 5 Amp, PS2 | 262 d | Mon 8/1/05 | Tue 8/15/06 | | 96% |
| 153 | PS2: Specification | 20 d | Mon 8/1/05 | Fri 8/26/05 | AD Electrical Engineer[50%],AD Electrical Technician[50%] | 100% |
| 154 | PS2: Identify Vendors | 4 d | Mon 8/29/05 | Thu 9/1/05 | AD Electrical Engineer[50%],AD Electrical Technician[50%] | 100% |
| 155 | PS2: Vendor Specification Review | 20 d | Mon 8/1/05 | Fri 8/26/05 | AD Electrical Engineer[5%] | 100% |
| 156 | PS2: Request For Inquiry Bids | 4 d | Mon 8/29/05 | Thu 9/1/05 | AD Electrical Engineer[13%] | 100% |
| 157 | PS2: Integration of PS into system | 176 d | Tue 11/15/05 | Mon 7/31/06 | AD Electrical Engineer[59%],AD Electrical Technician[59%] | 100% |
| 158 | PS2: Prototype Fabrication | 1 d | Wed 3/15/06 | Wed 3/15/06 | AD Electrical Engineer[50%],M&S[2,000] | 100% |
| 159 | PS2: Prototype Testing | 105 d | Thu 3/16/06 | Fri 8/11/06 | AD Electrical Engineer[88%],AD Electrical Technician[88%] | 90% |
| 160 | PS2: Approval For Production | 2 d | Mon 8/14/06 | Tue 8/15/06 | AD Electrical Engineer | 0% |
| 161 | Corrector Controller Design & Prototype, PCC | 178 d | Fri 1/20/06 | Fri 9/29/06 | | 66% |
| 162 | CC: Specification & Design | 93 d | Fri 1/20/06 | Wed 5/31/06 | AD Electrical Engineer[46%] | 100% |
| 163 | CC: Prototype Schematic Layout | 10 d | Thu 6/1/06 | Wed 6/14/06 | AD Electrical Engineer[50%] | 100% |
| 164 | CC: Prototype Parts Procurement | 1 d | Thu 7/27/06 | Thu 7/27/06 | AD Electrical Engineer[200%],M&S[4,000] | 100% |
| 165 | CC: Prototype PCB Layout | 12 d | Thu 6/15/06 | Fri 6/30/06 | AD Drafter/Designer[167%] | 100% |
| 166 | CC: Prototype PCB Fabrication | 1 d | Mon 7/24/06 | Mon 7/24/06 | AD Electrical Engineer[50%],M&S[3,000] | 100% |
| 167 | CC: Prototype Assembly, 5 Units | 21 d | Fri 7/28/06 | Fri 8/25/06 | PPD Electrical Technician[14%] | 20% |
| 168 | CC: Prototype Testing | 33 d | Fri 7/28/06 | Wed 9/13/06 | AD Electrical Engineer[45%] | 5% |
| 169 | CC: Prototype Approval | 2 d | Thu 9/14/06 | Fri 9/15/06 | AD Electrical Engineer[50%] | 0% |
| 170 | CC: Production Schematic Revisions | 4 d | Mon 9/18/06 | Thu 9/21/06 | AD Electrical Engineer[50%] | 0% |
| 171 | CC: Teststand Assembly | 10 d | Mon 9/18/06 | Fri 9/29/06 | AD Electrical Technician,M&S[5,000] | 0% |
| 172 | Local Display Design & Prototype | 63 d | Thu 8/17/06 | Tue 11/14/06 | | 0% |
| 173 | DD: Specification & Layout | 15 d | Thu 8/17/06 | Thu 9/7/06 | AD Electrical Engineer[50%] | 0% |
| 174 | DD: Hardware / Enclosure Design | 2 d | Fri 9/8/06 | Mon 9/11/06 | AD Electrical Engineer[50%] | 0% |
| 175 | DD: Prototype Schematic Layout | 10 d | Tue 9/12/06 | Mon 9/25/06 | AD Electrical Engineer[50%] | 0% |
| 176 | DD: Prototype Parts Procurement | 1 d | Mon 11/6/06 | Mon 11/6/06 | AD Electrical Engineer[200%],M&S[300] | 0% |
| 177 | DD: Prototype PCB Layout | 10 d | Tue 9/26/06 | Mon 10/9/06 | AD Electrical Technician | 0% |
| 178 | DD: Prototype PCB Fabrication | 1 d | Mon 10/30/06 | Mon 10/30/06 | AD Electrical Engineer[50%],M&S[1,200] | 0% |
| 179 | DD: Prototype Assembly, 2 Units | 2 d | Tue 11/7/06 | Wed 11/8/06 | AD Electrical Technician | 0% |
| 180 | DD: Prototype Testing | 1 d | Thu 11/9/06 | Thu 11/9/06 | AD Electrical Technician | 0% |
| 181 | DD: Prototype Approval | 1 d | Fri 11/10/06 | Fri 11/10/06 | AD Electrical Engineer | 0% |
| 182 | DD: Production Schematic Revisions | 2 d | Mon 11/13/06 | Tue 11/14/06 | AD Electrical Engineer | 0% |
| 183 | Long Straight PS Fabrication | 108 d | Tue 8/22/06 | Tue 1/30/07 | | 0% |
| 184 | Long Straight PS Production -- 50 Amp, PS1 | 108 d | Tue 8/22/06 | Tue 1/30/07 | | 0% |
| 185 | Long Straight PS1: Production Specification & Vendor Selection | 10 d | Tue 8/22/06 | Tue 9/5/06 | AD Electrical Engineer[50%] | 0% |
| 186 | Long Straight PS1: Production Oversight | 88 d | Wed 9/6/06 | Tue 1/16/07 | AD Electrical Engineer[14%] | 0% |
| 187 | Long Straight PS1: Prod Order Award, Fab & Delivery, 120 Units | 88 d | Wed 9/6/06 | Tue 1/16/07 | AD Mechanical Engineer[1%],M&S[450,000] | 0% |
| 188 | Long Straight PS1: Production Order Testing | 30 d | Wed 12/13/06 | Tue 1/30/07 | AD Electrical Technician[200%],AD Electrical Engineer[60%] | 0% |
| 189 | Long Straight PS1: Procure 160V Bulk Supplies & Filters, 6 Units | 50 d | Tue 8/22/06 | Tue 10/31/06 | M&S[52,000] | 0% |
| 190 | Long Straight PS Production -- 5 Amp, PS2 | 25 d | Wed 11/1/06 | Thu 12/7/06 | | 0% |
| 191 | Long Straight PS2: Production Order Fabrication, 24 Units | 1 d | Wed 11/1/06 | Wed 11/1/06 | AD Electrical Engineer,M&S[36,000] | 0% |
| 192 | Long Straight PS2: Production Order Testing | 24 d | Thu 11/2/06 | Thu 12/7/06 | AD Electrical Technician[50%],AD Electrical Engineer[13%] | 0% |
| 193 | Long Straight Installation | 333 d | Tue 8/22/06 | Tue 12/18/07 | | 0% |
| 194 | Long Straight PS & Controls Rack Assembly | 204 d | Tue 8/22/06 | Thu 6/14/07 | | 0% |
| 195 | CAMAC Long Straight Controller, CC | 75 d | Fri 9/22/06 | Fri 1/12/07 | | 0% |
| 196 | Long Straight CC: Production Parts Procurement, 36 Units | 1 d | Thu 11/2/06 | Thu 11/2/06 | AD Electrical Engineer[200%],M&S[21,600] | 0% |
| 197 | Long Straight CC: Production PCB Layout | 10 d | Fri 9/22/06 | Thu 10/5/06 | AD Drafter/Designer[50%] | 0% |
| 198 | Long Straight CC: Production PCB Fabrication, 36 Units | 1 d | Thu 11/2/06 | Thu 11/2/06 | AD Electrical Engineer[50%],M&S[12,600] | 0% |
| 199 | Long Straight CC: Production Assembly, 36 Units | 40 d | Fri 11/3/06 | Fri 1/5/07 | PPD Electrical Technician[50%] | 0% |
| 200 | Long Straight CC: Production Testing | 40 d | Fri 11/10/06 | Fri 1/12/07 | AD Electrical Technician[50%] | 0% |
| 201 | Long Straight Local Displays & Diagnostics, DD | 117 d | Tue 8/22/06 | Mon 2/12/07 | | 0% |
| 202 | Long Straight DD: Production Parts Procurement, 36 units | 1 d | Wed 1/3/07 | Wed 1/3/07 | AD Electrical Engineer[200%],M&S[10,800] | 0% |
| 203 | Long Straight DD: Production PCB Layout | 5 d | Wed 11/15/06 | Tue 11/21/06 | AD Electrical Technician[50%] | 0% |
| 204 | Long Straight DD: Production PCB Fabrication, 36 Units | 1 d | Thu 12/14/06 | Thu 12/14/06 | AD Electrical Engineer[50%],M&S[3,600] | 0% |
| 205 | Long Straight DD: Production Assembly, 36 Units | 9 d | Thu 1/4/07 | Wed 1/17/07 | AD Electrical Technician[50%] | 0% |
| 206 | Long Straight DD: Production Testing | 18 d | Thu 1/18/07 | Mon 2/12/07 | AD Electrical Technician[50%] | 0% |
| 207 | Long Straight DD: Documentation | 20 d | Mon 11/13/06 | Tue 12/12/06 | AD Electrical Engineer[25%] | 0% |
| 208 | Long Straight DD: HRM Analog Readback Electronics, 6 Units | 60 d | Tue 8/22/06 | Tue 11/14/06 | AD Electrical Engineer[8%],AD Electrical Technician[34%],M&S[15,000] | 0% |
| 209 | Long Straight Rack Installation, RI | 204 d | Tue 8/22/06 | Thu 6/14/07 | | 0% |
| 210 | Long Straight RI: Identify New Rack Locations | 2 d | Tue 8/22/06 | Wed 8/23/06 | AD Electrical Technician[50%] | 0% |
| 211 | Long Straight RI: Specify Rack Layout & Cooling | 10 d | Thu 8/24/06 | Thu 9/7/06 | AD Electrical Technician[50%] | 0% |
| 212 | Long Straight RI: Create Drawings for Rack Layout | 5 d | Fri 9/8/06 | Thu 9/14/06 | AD Electrical Technician[50%] | 0% |
| 213 | Long Straight RI: Prepare New Rack Locations | 5 d | Thu 8/24/06 | Wed 8/30/06 | AD Electrical Technician | 0% |
| 214 | Long Straight RI: Transport Racks from Storage | 5 d | Thu 8/31/06 | Thu 9/7/06 | AD Electrical Technician | 0% |
| 215 | Long Straight RI: Prepare Racks with Equip. Support Hardware | 5 d | Fri 9/15/06 | Thu 9/21/06 | AD Electrical Technician,M&S[6,000] | 0% |
| 216 | Long Straight RI: AC Power Installation | 21 d | Fri 9/22/06 | Fri 10/20/06 | AD Electrical Engineer[20%],M&S[20,000] | 0% |
| 217 | Long Straight RI: Install Rack Cooling | 5 d | Mon 10/23/06 | Fri 10/27/06 | AD Electrical Technician | 0% |
| 218 | Long Straight RI: Install Bulk Power Supplies, 6 each 15kW Units | 5 d | Wed 11/1/06 | Tue 11/7/06 | AD Electrical Technician | 0% |
| 219 | Long Straight RI: Install Power Amplifiers | 10 d | Wed 1/31/07 | Tue 2/13/07 | AD Electrical Technician | 0% |
| 220 | Long Straight RI: Install Controls & Diagnostic Equip. | 40 d | Wed 2/14/07 | Tue 4/10/07 | AD Electrical Technician | 0% |
| 221 | Long Straight RI: Power Amplifier Test Design & Hazard Analysis | 10 d | Fri 9/15/06 | Thu 9/28/06 | AD Electrical Engineer[50%] | 0% |
| 222 | Long Straight RI: Test Interlocks | 10 d | Fri 3/30/07 | Thu 4/12/07 | AD Electrical Technician | 0% |
| 223 | Long Straight RI: Test Power Amplifiers w/Load | 40 d | Fri 4/13/07 | Fri 6/8/07 | AD Electrical Engineer[50%] | 0% |
| 224 | Long Straight RI: Test Controls | 20 d | Thu 5/17/07 | Thu 6/14/07 | AD Electrical Technician[50%] | 0% |
| 225 | Long Straight Cabling, CBL | 155 d | Wed 11/1/06 | Fri 6/15/07 | | 0% |
| 226 | Long Straight CBL: Specify Power Cables & Connectors | 4 d | Wed 11/1/06 | Mon 11/6/06 | AD Electrical Engineer[50%] | 0% |
| 227 | Long Straight CBL: Bid & Procure Power Cables | 1 d | Wed 1/24/07 | Wed 1/24/07 | AD Electrical Engineer[200%],M&S[20,000] | 0% |
| 228 | Long Straight CBL: Procure Power Cable Connectors | 1 d | Wed 2/7/07 | Wed 2/7/07 | AD Electrical Engineer[300%] | 0% |
| 229 | Long Straight CBL: Power Cable is Delivered | 1 d | Thu 2/8/07 | Thu 2/8/07 | M&S[1,152] | 0% |
| 230 | Long Straight CBL: Pull Power Cables from Racks to Magnets | 10 d | Mon 6/4/07 | Fri 6/15/07 | AD Electrical Engineer[10%],M&S[14,000] | 0% |
| 231 | Long Straight CBL: Specifying Control Cables & Connectors | 8 d | Wed 11/15/06 | Tue 11/28/06 | AD Electrical Engineer[50%] | 0% |
| 232 | Long Straight CBL: Procure Control Cable & Connectors | 1 d | Tue 1/16/07 | Tue 1/16/07 | AD Electrical Engineer[200%],M&S[26,208] | 0% |
| 233 | Long Straight CBL: Routing Control Cables | 4 d | Wed 1/17/07 | Mon 1/22/07 | AD Electrical Engineer[10%],M&S[2,800] | 0% |
| 234 | Long Straight CBL: Terminating Control Cables | 40 d | Tue 1/23/07 | Mon 3/19/07 | AD Electrical Technician | 0% |
| 235 | Long Straight Magnet Installation | 230 d | Tue 8/22/06 | Mon 7/23/07 | | 0% |
| 236 | Long Straight Booster Modification (BM) | 203 d | Tue 8/22/06 | Wed 6/13/07 | | 0% |
| 237 | Long Straight BM: Mech Design of New Straight & Supports | 92 d | Tue 8/22/06 | Fri 1/5/07 | AD Mechanical Engineer[136%],AD Drafter/Designer[136%] | 0% |
| 238 | Long Straight BM: Procure & Machining of Initial LS Spool Piece | 1 d | Mon 3/5/07 | Mon 3/5/07 | AD Mechanical Engineer[200%],M&S[1,500] | 0% |
| 239 | Long Straight BM: Assembly of Initial LS Spool Piece | 4 d | Tue 3/6/07 | Fri 3/9/07 | AD Mechanical Technician[200%],AD Mechanical Engineer[9%],M&S[100] | 0% |
| 240 | Long Straight BM: LS Initial Spool Piece Examination in Booster Enclosure | 6 d | Mon 3/12/07 | Mon 3/19/07 | AD Mechanical Technician[200%],AD Mechanical Engineer | 0% |
| 241 | Long Straight BM: Develop Drawings for Long Straight | 20 d | Mon 1/8/07 | Mon 2/5/07 | AD Drafter/Designer | 0% |
| 242 | Long Straight BM: Procure & Machining of LS Spool Piece Components | 1 d | Mon 4/30/07 | Mon 4/30/07 | AD Mechanical Engineer[200%],M&S[24,000] | 0% |
| 243 | Long Straight BM: Enclosure Installation Hazard Analysis | 12 d | Tue 2/6/07 | Wed 2/21/07 | AD Engineer[25%] | 0% |
| 244 | Long Straight BM: Enclosure Work Safety Review | 2 d | Thu 2/22/07 | Fri 2/23/07 | AD Engineer[50%] | 0% |
| 245 | Long Straight BM: Removal of Long Straight Sections | 8 d | Mon 6/4/07 | Wed 6/13/07 | AD Mechanical Technician[375%],AD Mechanical Engineer[31%] | 0% |
| 246 | Phase 1 Long Straight Spool Piece Assy, CLS | 58 d | Tue 5/1/07 | Mon 7/23/07 | | 0% |
| 247 | Long Straight CLS: Component Inspection & Cleaning | 3 d | Tue 5/1/07 | Thu 5/3/07 | AD Mechanical Technician,AD Mechanical Engineer[13%] | 0% |
| 248 | Long Straight CLS: Spool Piece Welding & Assy Upstairs | 9 d | Fri 5/4/07 | Wed 5/16/07 | AD Mechanical Technician,AD Mechanical Engineer[11%] | 0% |
| 249 | Long Straight CLS: Spool Piece Leak Checking | 9 d | Fri 5/18/07 | Thu 5/31/07 | AD Mechanical Technician,AD Mechanical Engineer[11%] | 0% |
| 250 | Long Straight CLS: Install Magnets, Stands & Spool Pieces in Enclosure | 10 d | Fri 6/8/07 | Thu 6/21/07 | AD Mechanical Technician[400%],AD Mechanical Engineer[43%] | 0% |
| 251 | Long Straight CLS: Corrector Cooling Water Connection | 3 d | Tue 6/26/07 | Thu 6/28/07 | AD Mechanical Technician[200%],AD Mechanical Engineer[21%] | 0% |
| 252 | Long Straight CLS: Spool Piece Cabling | 6 d | Wed 6/27/07 | Thu 7/5/07 | AD Electrical Technician | 0% |
| 253 | Long Straight CLS: Spool Piece Power Testing | 6 d | Fri 7/6/07 | Fri 7/13/07 | AD Electrical Engineer | 0% |
| 254 | Long Straight CLS: Corrector & BPM Alignment | 6 d | Mon 7/16/07 | Mon 7/23/07 | PPD Survey Technician[200%] | 0% |
| 255 | Long Straight Corrector Installation Complete | 0 d | Mon 7/23/07 | Mon 7/23/07 | | 0% |
| 256 | Cooling Water Plumbing, LCW | 101 d | Tue 2/6/07 | Wed 6/27/07 | | 0% |
| 257 | Long Straight LCW: Procurement of Materials, Phase 2 | 25 d | Tue 2/6/07 | Mon 3/12/07 | AD Mechanical Engineer[8%],M&S[5,014] | 0% |
| 258 | Long Straight LCW: Build Sub-Headers & Leads, Phase 2 | 9 d | Fri 6/15/07 | Wed 6/27/07 | AD Mechanical Engineer[25%],AD Mechanical Technician[200%],M&S[18,830] | 0% |
| 259 | Long Straight System Installation Review | 1 d | Mon 2/26/07 | Mon 2/26/07 | AD Mechanical Engineer[500%],AD Electrical Engineer[500%],AD Physicist[500%] | 0% |
| 260 | Long Straight Applications Software Development | 333 d | Tue 8/22/06 | Tue 12/18/07 | | 0% |
| 261 | Long Straight Appl SW Dev: Specifications | 63 d | Tue 8/22/06 | Fri 11/17/06 | AD Physicist[25%] | 0% |
| 262 | Long Straight Appl SW Dev: Crate Level DAQ Software Development | 63 d | Mon 11/20/06 | Fri 2/23/07 | AD Computer Professional[50%] | 0% |
| 263 | Long Straight Appl SW Dev: Application Programming | 250 d | Wed 12/20/06 | Tue 12/18/07 | AD Computer Professional[50%] | 0% |
| 264 | Short Straight Magnets Production | 255 d | Tue 5/1/07 | Mon 5/5/08 | | 0% |
| 265 | Short Straight Magnets Design & Procurement | 120 d | Tue 5/1/07 | Thu 10/18/07 | | 0% |
| 266 | Design Short Straight Production Units (24) | 10 d | Wed 5/2/07 | Tue 5/15/07 | TD Mechanical Engineer[158%],TD Mechanical Technician[364%] | 0% |
| 267 | Procure Short Straight Components | 120 d | Tue 5/1/07 | Thu 10/18/07 | TD Mechanical Engineer[1%],TD Mechanical Technician[10%],M&S[579,707] | 0% |
| 268 | Short Straight Magnets Fab & Test | 210 d | Thu 7/5/07 | Mon 5/5/08 | | 0% |
| 269 | Fabricate Short Straight Production Units (24) | 90 d | Thu 7/5/07 | Thu 11/8/07 | TD Mechanical Engineer[233%],TD Mechanical Technician[717%] | 0% |
| 270 | Test Short Straight Production Units | 100 d | Tue 12/11/07 | Mon 5/5/08 | | 0% |
| 271 | Short Straight Integrated BPMs Prep Procurement | 200 d | Thu 7/5/07 | Mon 4/21/08 | TD Mechanical Technician[23%],M&S[36,720] | 0% |
| 272 | Short Straight Magnets Ready for Installation | 0 d | Mon 5/5/08 | Mon 5/5/08 | | 0% |
| 273 | Short Straight PS Fabrication | 158 d | Wed 5/2/07 | Fri 12/14/07 | | 0% |
| 274 | Short Straight PS Production -- 50 Amp, PS1 | 158 d | Wed 5/2/07 | Fri 12/14/07 | | 0% |
| 275 | Short Straight PS1: Production Specification & Vendor Selection | 10 d | Wed 5/2/07 | Tue 5/15/07 | AD Electrical Engineer[50%] | 0% |
| 276 | Short Straight PS1: Production Oversight | 100 d | Wed 5/16/07 | Fri 10/5/07 | AD Electrical Engineer[13%] | 0% |
| 277 | Short Straight PS1: Production Order Award & Fabrication, 120 Units | 88 d | Wed 5/16/07 | Wed 9/19/07 | AD Electrical Engineer[2%],M&S[450,000] | 0% |
| 278 | Short Straight PS1: Production Order Testing | 48 d | Mon 10/8/07 | Fri 12/14/07 | AD Electrical Technician[125%],AD Electrical Engineer[31%] | 0% |
| 279 | Short Straight PS1: Procure 160V Bulk Supplies & Filters, 6 units | 50 d | Wed 5/2/07 | Thu 7/12/07 | M&S[52,000] | 0% |
| 280 | Short Straight PS Production -- 5 Amp, PS2 | 25 d | Wed 5/2/07 | Wed 6/6/07 | | 0% |
| 281 | Short Straight PS2: Production Order Fabrication, 24 Units | 1 d | Wed 5/2/07 | Wed 5/2/07 | AD Electrical Engineer,M&S[36,000] | 0% |
| 282 | Short Straight PS2: Production Order Testing | 24 d | Thu 5/3/07 | Wed 6/6/07 | AD Electrical Technician[50%],AD Electrical Engineer[13%] | 0% |
| 283 | Short Straight Installation | 311 d | Wed 5/2/07 | Fri 7/25/08 | | 0% |
| 284 | Short Straight PS & Controls Rack Assembly | 278 d | Wed 5/2/07 | Mon 6/9/08 | | 0% |
| 285 | CAMAC Short Straight Controller, CC | 75 d | Wed 5/2/07 | Thu 8/16/07 | | 0% |
| 286 | Short Straight CC: Production Parts Procurement, 36 Units | 1 d | Wed 5/2/07 | Wed 5/2/07 | AD Electrical Engineer[200%],M&S[21,600] | 0% |
| 287 | Short Straight CC: Production PCB Layout | 10 d | Wed 5/2/07 | Tue 5/15/07 | AD Drafter/Designer[50%] | 0% |
| 288 | Short Straight CC: Production PCB Fabrication, 36 Units | 1 d | Wed 6/13/07 | Wed 6/13/07 | AD Electrical Engineer[50%],M&S[12,600] | 0% |
| 289 | Short Straight CC: Production Assembly, 36 Units | 40 d | Thu 6/14/07 | Thu 8/9/07 | PPD Electrical Technician[50%] | 0% |
| 290 | Short Straight CC: Production Testing | 40 d | Thu 6/21/07 | Thu 8/16/07 | AD Electrical Technician[50%] | 0% |
| 291 | Short Straight Local Displays & Diagnostics, DD | 60 d | Mon 7/30/07 | Mon 10/22/07 | | 0% |
| 292 | Short Straight DD: Production Parts Procurement, 36 units | 1 d | Mon 7/30/07 | Mon 7/30/07 | AD Electrical Engineer[200%],M&S[10,800] | 0% |
| 293 | Short Straight DD: Production PCB Layout | 5 d | Mon 7/30/07 | Fri 8/3/07 | AD Electrical Technician[50%] | 0% |
| 294 | Short Straight DD: Production PCB Fabrication, 36 Units | 1 d | Fri 8/24/07 | Fri 8/24/07 | AD Electrical Engineer[50%],M&S[3,600] | 0% |
| 295 | Short Straight DD: Production Assembly, 36 Units | 9 d | Mon 8/27/07 | Fri 9/7/07 | AD Electrical Technician[50%] | 0% |
| 296 | Short Straight DD: Production Testing | 18 d | Mon 9/10/07 | Wed 10/3/07 | AD Electrical Technician[50%] | 0% |
| 297 | Short Straight DD: Documentation | 20 d | Mon 7/30/07 | Fri 8/24/07 | AD Electrical Engineer[25%] | 0% |
| 298 | Short Straight DD: HRM Analog Readback Electronics, 6 Units | 60 d | Mon 7/30/07 | Mon 10/22/07 | AD Electrical Engineer[8%],AD Electrical Technician[34%],M&S[15,000] | 0% |
| 299 | Short Straight Rack Installation, RI | 278 d | Wed 5/2/07 | Mon 6/9/08 | | 0% |
| 300 | Short Straight RI: Identify New Rack Locations | 2 d | Wed 5/2/07 | Thu 5/3/07 | AD Electrical Technician[50%] | 0% |
| 301 | Short Straight RI: Specify Rack Layout & Cooling | 10 d | Fri 5/4/07 | Thu 5/17/07 | AD Electrical Technician[50%] | 0% |
| 302 | Short Straight RI: Create Drawings for Rack Layout | 5 d | Fri 5/18/07 | Thu 5/24/07 | AD Electrical Technician[50%] | 0% |
| 303 | Short Straight RI: Prepare New Rack Locations | 5 d | Fri 5/4/07 | Thu 5/10/07 | AD Electrical Technician | 0% |
| 304 | Short Straight RI: Transport Racks from Storage | 5 d | Fri 5/11/07 | Thu 5/17/07 | AD Electrical Technician | 0% |
| 305 | Short Straight RI: Prepare Racks with Equip. Support Hardware | 5 d | Fri 5/25/07 | Fri 6/1/07 | AD Electrical Technician,M&S[6,000] | 0% |
| 306 | Short Straight RI: AC Power Installation | 21 d | Mon 6/4/07 | Mon 7/2/07 | AD Electrical Engineer[20%],M&S[20,000] | 0% |
| 307 | Short Straight RI: Install Rack Cooling | 5 d | Tue 7/3/07 | Tue 7/10/07 | AD Electrical Technician | 0% |
| 308 | Short Straight RI: Install Bulk Power Supplies, 6 each 15kW Units | 5 d | Fri 7/13/07 | Thu 7/19/07 | AD Electrical Technician | 0% |
| 309 | Short Straight RI: Install Power Amplifiers | 10 d | Mon 12/17/07 | Thu 1/3/08 | AD Electrical Technician | 0% |
| 310 | Short Straight RI: Install Controls & Diagnostic Equip. | 40 d | Fri 1/4/08 | Fri 2/29/08 | AD Electrical Technician | 0% |
| 311 | Short Straight RI: Power Amplifier Test Design & Hazard Analysis | 10 d | Fri 5/25/07 | Fri 6/8/07 | AD Electrical Engineer[50%] | 0% |
| 312 | Short Straight RI: Test Interlocks | 10 d | Mon 3/3/08 | Fri 3/14/08 | AD Electrical Technician | 0% |
| 313 | Short Straight RI: Test Power Amplifiers w/Load | 40 d | Mon 3/17/08 | Fri 5/9/08 | AD Electrical Engineer[50%] | 0% |
| 314 | Short Straight RI: Test Controls | 20 d | Mon 5/12/08 | Mon 6/9/08 | AD Electrical Technician[50%] | 0% |
| 315 | Short Straight Cabling, CBL | 143 d | Wed 5/2/07 | Wed 11/21/07 | | 0% |
| 316 | Short Straight CBL: Specify Power Cables & Connectors | 4 d | Wed 5/2/07 | Mon 5/7/07 | AD Electrical Engineer[50%] | 0% |
| 317 | Short Straight CBL: Bid & Procure Power Cables | 1 d | Wed 7/18/07 | Wed 7/18/07 | AD Electrical Engineer[200%],M&S[20,000] | 0% |
| 318 | Short Straight CBL: Procure Power Cable Connectors | 1 d | Tue 6/19/07 | Tue 6/19/07 | AD Electrical Engineer[50%] | 0% |
| 319 | Short Straight CBL: Power Cable is Delivered | 1 d | Wed 6/20/07 | Wed 6/20/07 | M&S[1,152] | 0% |
| 320 | Short Straight CBL: Pull Power Cables from Racks to Magnets | 10 d | Thu 7/19/07 | Wed 8/1/07 | AD Electrical Engineer[10%],M&S[14,000] | 0% |
| 321 | Short Straight CBL: Specifying Control Cables & Connectors | 8 d | Mon 7/30/07 | Wed 8/8/07 | AD Electrical Engineer[50%] | 0% |
| 322 | Short Straight CBL: Procure Control Cable & Connectors | 1 d | Thu 9/20/07 | Thu 9/20/07 | AD Electrical Engineer[200%],M&S[26,208] | 0% |
| 323 | Short Straight CBL: Routing Control Cables | 4 d | Fri 9/21/07 | Wed 9/26/07 | AD Electrical Engineer[10%],M&S[2,800] | 0% |
| 324 | Short Straight CBL: Terminating Control Cables | 40 d | Thu 9/27/07 | Wed 11/21/07 | AD Electrical Technician | 0% |
| 325 | Short Straightector Magnet Installation | 311 d | Wed 5/2/07 | Fri 7/25/08 | | 0% |
| 326 | Short Straight Booster Modification, BM | 280 d | Wed 5/2/07 | Wed 6/11/08 | | 0% |
| 327 | Short Straight BM: Design of New Short Straight Support | 55 d | Wed 5/16/07 | Thu 8/2/07 | AD Mechanical Engineer,AD Drafter/Designer | 0% |
| 328 | Short Straight BM: Design of New SS Spool Piece | 10 d | Wed 5/2/07 | Tue 5/15/07 | AD Mechanical Engineer,AD Drafter/Designer | 0% |
| 329 | Short Straight BM: Procure & Machining of Initial SS Spool Piece | 1 d | Fri 9/28/07 | Fri 9/28/07 | AD Mechanical Engineer[200%],M&S[1,500] | 0% |
| 330 | Short Straight BM: Assembly of Initial SS Spool Piece | 4 d | Mon 10/1/07 | Thu 10/4/07 | AD Mechanical Technician[200%],AD Mechanical Engineer[13%],M&S[100] | 0% |
| 331 | Short Straight BM: SS Initial Spool Piece Examination in Booster Enclosure | 6 d | Fri 10/5/07 | Fri 10/12/07 | AD Mechanical Technician[200%],AD Mechanical Engineer | 0% |
| 332 | Short Straight BM: Develop Drawings for Short Straight | 10 d | Mon 10/15/07 | Fri 10/26/07 | AD Drafter/Designer | 0% |
| 333 | Short Straight BM: Procure & Machining of SS Support | 1 d | Tue 1/29/08 | Tue 1/29/08 | AD Mechanical Engineer[200%],AD Drafter/Designer[80%],M&S[6,000] | 0% |
| 334 | Short Straight BM: Procure & Machining of SS Spool Piece Components | 1 d | Thu 12/27/07 | Thu 12/27/07 | AD Mechanical Engineer[200%],AD Drafter/Designer[80%],AD Mechanical Technician,M&S[24,000] | 0% |
| 335 | Short Straight BM: Enclosure Installation Hazard Analysis | 12 d | Mon 10/29/07 | Tue 11/13/07 | AD Engineer[25%] | 0% |
| 336 | Short Straight BM: Enclosure Work Safety Review | 2 d | Wed 11/14/07 | Thu 11/15/07 | AD Engineer[50%] | 0% |
| 337 | Short Straight BM: Removal of Short Straight Sections | 8 d | Mon 6/2/08 | Wed 6/11/08 | AD Mechanical Technician[375%],AD Mechanical Engineer[31%] | 0% |
| 338 | Phase 2 Short Straight Spool Piece Assy, CSS | 246 d | Fri 8/3/07 | Fri 7/25/08 | | 0% |
| 339 | Short Straight CSS: Assembly & Installation Planning & Hazard Analysis | 5 d | Fri 8/3/07 | Thu 8/9/07 | AD Engineer | 0% |
| 340 | Short Straight CSS: Component Inspection & Cleaning | 3 d | Fri 12/28/07 | Thu 1/3/08 | AD Mechanical Technician,AD Mechanical Engineer[13%] | 0% |
| 341 | Short Straight CSS: Spool Piece Welding & Assy Upstairs | 6 d | Fri 1/4/08 | Fri 1/11/08 | AD Mechanical Technician,AD Mechanical Engineer[10%] | 0% |
| 342 | Short Straight CSS: Spool Piece Leak Checking | 6 d | Mon 1/7/08 | Mon 1/14/08 | AD Mechanical Technician,AD Mechanical Engineer[10%] | 0% |
| 343 | Short Straight CSS: Install Magnets, Stands & Spool Pieces in Enclosure | 10 d | Fri 6/6/08 | Thu 6/19/08 | AD Mechanical Technician[400%],AD Mechanical Engineer[43%] | 0% |
| 344 | Short Straight CSS: Corrector Cooling Water Connection | 6 d | Thu 6/19/08 | Thu 6/26/08 | AD Mechanical Technician,AD Mechanical Engineer[10%] | 0% |
| 345 | Short Straight CSS: Spool Piece Cabling | 6 d | Fri 6/27/08 | Mon 7/7/08 | AD Electrical Technician | 0% |
| 346 | Short Straight CSS: Spool Piece Power Testing | 6 d | Tue 7/8/08 | Tue 7/15/08 | AD Electrical Engineer | 0% |
| 347 | Short Straight CSS: Corrector & BPM Alignment | 6 d | Wed 7/16/08 | Wed 7/23/08 | PPD Survey Technician[200%] | 0% |
| 348 | Short Straight Corrector Installation Complete | 0 d | Fri 7/25/08 | Fri 7/25/08 | | 0% |
| 349 | Short Straight Cooling Water Plumbing, LCW | 229 d | Mon 7/30/07 | Wed 6/25/08 | | 0% |
| 350 | Short Straight LCW: Water Circuit Design | 20 d | Mon 7/30/07 | Fri 8/24/07 | AD Mechanical Engineer[50%] | 0% |
| 351 | Short Straight LCW: Procurement of Materials, Phase 2 Split betw Long & Short | 1 d | Mon 10/29/07 | Mon 10/29/07 | AD Mechanical Engineer[25%],M&S[5,014] | 0% |
| 352 | Short Straight LCW: Build Sub-Headers & Leads (Phase 2) Split betw Long & Short | 9 d | Fri 6/13/08 | Wed 6/25/08 | AD Mechanical Engineer[25%],AD Mechanical Technician,M&S[26,600] | 0% |
| 353 | Short Straight Applications Software Development | 311 d | Wed 5/2/07 | Fri 7/25/08 | | 0% |
| 354 | Short Straight Appl SW Dev: Specifications | 41 d | Wed 5/2/07 | Thu 6/28/07 | AD Physicist[38%] | 0% |
| 355 | Short Straight Appl SW Dev: Crate Level DAQ Software Development | 63 d | Fri 6/29/07 | Thu 9/27/07 | AD Computer Professional[50%] | 0% |
| 356 | Short Straight Appl SW Dev: Application Programming | 250 d | Mon 7/30/07 | Fri 7/25/08 | AD Computer Professional[50%] | 0% |
| 357 | Commission Corrector System | 125 d | Thu 10/16/08 | Fri 4/17/09 | AD Physicist | 0% |
| 358 | Corrector System Complete | 0 d | Fri 4/17/09 | Fri 4/17/09 | | 0% |
| 359 | Long Straight AIP Project Management | 333 d | Tue 8/22/06 | Tue 12/18/07 | AD Electrical Engineer[22%] | 0% |
| 360 | Short Straight AIP Project Management | 493 d | Wed 5/2/07 | Fri 4/17/09 | AD Electrical Engineer[15%] | 0% |
| 361 | Prepare AIP Documentation | 482 d | Thu 9/1/05 | Fri 8/3/07 | | 98% |
| 362 | Develop AIP Packages | 185 d | Thu 9/1/05 | Tue 5/30/06 | AD Electrical Engineer[50%],AD Project Manager[14%] | 100% |
| 363 | Corrector System Technical Review | 1 d | Mon 8/14/06 | Mon 8/14/06 | AD Mechanical Engineer[500%],AD Electrical Engineer[500%],AD Physicist[500%] | 0% |
| 364 | Long Straight Corrector AIPs Approved | 0 d | Mon 8/21/06 | Mon 8/21/06 | | 0% |
| 365 | Short Straight Corrector AIPs Approved | 1 d | Tue 5/1/07 | Tue 5/1/07 | | 0% |
| 366 | Review Booster Modifications Design | 1 d | Fri 8/3/07 | Fri 8/3/07 | AD Mechanical Engineer,AD Physicist | 0% |
| 367 | Booster LCW Modifications | 109 d | Tue 11/1/05 | Tue 4/11/06 | | 100% |
| 368 | Long Straight LCW: Water Circuit Design | 70 d | Tue 11/1/05 | Wed 2/15/06 | AD Mechanical Engineer[24%],AD Drafter/Designer[76%] | 100% |
| 369 | Long Straight LCW: Procurement of Materials, Phase 1 All w/Long | 34 d | Tue 12/27/05 | Wed 2/15/06 | AD Mechanical Engineer[9%],M&S[16,668] | 100% |
| 370 | Long Straight LCW: Tee in to Existing Header ( Phase 1) All w/Long | 30 d | Wed 3/1/06 | Tue 4/11/06 | AD Mechanical Engineer[12%],AD Mechanical Technician[23%],M&S[56,000] | 100% |
| 371 | Corrector Magnets Spares (12) | 130 d | Tue 8/22/06 | Thu 3/1/07 | TD Mechanical Engineer[87%],TD Mechanical Technician[267%],M&S[314,853] | 0% |
| 372 | 30 Hz Harmonic | 398 d | Mon 1/3/05 | Mon 7/31/06 | | 100% |
| 373 | 30 Hz Harmonic Prototype | 357 d | Mon 1/3/05 | Thu 6/1/06 | | 100% |
| 374 | 30 Hz Harmonic Prototype | 357 d | Mon 1/3/05 | Thu 6/1/06 | AD Physicist[9%],AD Electrical Engineer[8%],M&S[24,541] | 100% |
| 375 | Review 30 Hz Harmonic Concept | 1 d | Fri 2/24/06 | Fri 2/24/06 | AD Electrical Engineer[500%],AD Physicist[500%] | 100% |
| 376 | 30 Hz Harmonic Project Decision | 0 d | Fri 2/24/06 | Fri 2/24/06 | | 100% |
| 377 | 30Hz Girder Design | 170 d | Tue 6/21/05 | Fri 2/24/06 | AD Mechanical Engineer[47%] | 100% |
| 378 | 30 Hz Harmonic Production | 20 d | Mon 7/3/06 | Mon 7/31/06 | | 100% |
| 379 | 30Hz Procurement Preparation (Deleted in CR#14) | 20 d | Mon 7/3/06 | Mon 7/31/06 | | 100% |
| 380 | GMPS Modification (Deleted in CR#14) | 20 d | Mon 7/3/06 | Mon 7/31/06 | | 100% |
| 381 | 30Hz Installation (Deleted in CR#14) | 20 d | Mon 7/3/06 | Mon 7/31/06 | | 100% |
| 382 | 30Hz Installation Complete (Deleted in CR#14) | 0 d | Mon 7/31/06 | Mon 7/31/06 | | 100% |
| 383 | Gamma-t System | 813 d | Mon 5/2/05 | Fri 7/25/08 | | 32% |
| 384 | Gamma-t System Studies | 205 d | Mon 5/2/05 | Fri 2/24/06 | | 100% |
| 385 | Gamma-t Studies | 205 d | Mon 5/2/05 | Fri 2/24/06 | AD Physicist[41%] | 100% |
| 386 | Gamma-t Studies Complete | 0 d | Fri 2/24/06 | Fri 2/24/06 | | 100% |
| 387 | Gamma-t Review/Project Decision | 1 d | Fri 2/24/06 | Fri 2/24/06 | AD Electrical Engineer[500%],AD Physicist[500%] | 100% |
| 388 | New Gamma-t System | 531 d | Thu 6/15/06 | Fri 7/25/08 | | 5% |
| 389 | New Gamma-t System Design | 132 d | Thu 6/15/06 | Thu 12/21/06 | TD Drafter/Designer[25%],TD Mechanical Engineer[8%] | 20% |
| 390 | New Gamma-t System Mechanical Design | 125 d | Tue 1/2/07 | Wed 6/27/07 | AD Drafter/Designer,AD Mechanical Engineer | 0% |
| 391 | New Gamma-t System Procure/Fab | 125 d | Thu 6/28/07 | Thu 12/27/07 | TD Mechanical Technician[150%],M&S[200,000] | 0% |
| 392 | New Gamma-t System Procure/Fab - AD Support | 125 d | Thu 6/28/07 | Thu 12/27/07 | AD Mechanical Engineer[10%],AD Drafter/Designer[10%] | 0% |
| 393 | New Gamma-t System Install | 21 d | Thu 6/26/08 | Fri 7/25/08 | AD Electrical Engineer[25%],AD Mechanical Engineer,AD Mechanical Technician[200%] | 0% |
| 394 | New Gamma-t Installation Complete | 0 d | Fri 7/25/08 | Fri 7/25/08 | | 0% |
| 395 | Booster RF Cavity Cooling | 333 d | Tue 1/4/05 | Fri 4/28/06 | | 100% |
| 396 | Stainless Steel Flex Tubes | 333 d | Tue 1/4/05 | Fri 4/28/06 | | 100% |
| 397 | Flex Tube Fab | 39 d | Tue 1/4/05 | Mon 2/28/05 | AD Mechanical Technician[16%] | 100% |
| 398 | Re-Install Flex Tubes | 40 d | Mon 3/6/06 | Fri 4/28/06 | AD RF Tech[38%],M&S[3,000] | 100% |
| 399 | Flex Tube Installation Complete | 0 d | Fri 4/28/06 | Fri 4/28/06 | | 100% |
| 400 | Booster Solid State RF Upgrade | 500 d | Mon 10/3/05 | Fri 9/28/07 | | 42% |
| 401 | Booster Dump Relocation | 272 d | Mon 5/2/05 | Wed 5/31/06 | | 100% |
| 402 | Booster Dump Relocation Design | 128 d | Mon 5/2/05 | Mon 10/31/05 | AD Mechanical Engineer[14%],AD Electrical Engineer[14%],AD Drafter/Designer[25%],M&S[11,000] | 100% |
| 403 | Review Booster Dump Relocation Design | 1 d | Tue 7/5/05 | Tue 7/5/05 | | 100% |
| 404 | Booster Dump Relocation Misc Fabrication | 101 d | Tue 11/1/05 | Thu 3/30/06 | AD Mechanical Engineer[10%],AD Drafter/Designer[5%],M&S[10,000] | 100% |
| 405 | Booster Dump Relocation Install | 250 d | Mon 5/16/05 | Fri 5/12/06 | | 100% |
| 406 | Booster Dump Relocation Remove Shielding Wall | 6 d | Mon 2/27/06 | Mon 3/6/06 | AD Mechanical Engineer[33%],AD Mechanical Technician[133%],M&S[41,000] | 100% |
| 407 | Booster Dump Relocation Design Monorail | 49 d | Mon 8/1/05 | Fri 10/7/05 | AD Mechanical Engineer[50%],AD Drafter/Designer[30%] | 100% |
| 408 | Booster Dump Relocation Remove Existing MP01 Septum | 1 d | Fri 3/3/06 | Fri 3/3/06 | AD Mechanical Technician[300%],AD Mechanical Engineer[20%] | 100% |
| 409 | Booster Dump Relocation Review Monorail Design | 15 d | Mon 10/10/05 | Fri 10/28/05 | AD Mechanical Engineer[33%] | 100% |
| 410 | Booster Dump Relocation Install Replacement MP01 (Old MI-8) Septum | 5 d | Fri 3/24/06 | Thu 3/30/06 | AD Mechanical Technician[300%],AD Mechanical Engineer[30%] | 100% |
| 411 | Booster Dump Relocation Install Monorail | 4 d | Tue 3/7/06 | Fri 3/10/06 | AD Mechanical Engineer[38%],AD Mechanical Technician[125%],M&S[5,000] | 100% |
| 412 | Booster Dump Relocation Run Power to MP01 Septum incl Cables & Cable Trays | 210 d | Wed 6/1/05 | Mon 4/3/06 | AD Electrical Engineer[25%],AD Electrical Technician[50%],M&S[48,000] | 100% |
| 413 | Booster Dump Relocation Run Cooling Water to MP01 | 16 d | Mon 3/20/06 | Mon 4/10/06 | AD Mechanical Technician[16%],AD Mechanical Engineer[6%],M&S[4,000] | 100% |
| 414 | Booster Dump Relocation Remove Booster Kickers | 1 d | Mon 3/6/06 | Mon 3/6/06 | AD Mechanical Technician[300%],AD Mechanical Engineer | 100% |
| 415 | Booster Dump Relocation Install Booster Kickers | 16 d | Mon 3/20/06 | Mon 4/10/06 | AD Mechanical Technician[94%],AD Mechanical Engineer[9%] | 100% |
| 416 | Booster Dump Relocation SQF Quad Removal | 15 d | Tue 3/7/06 | Mon 3/27/06 | AD Mechanical Technician[20%],AD Mechanical Engineer[2%] | 100% |
| 417 | Booster Dump Relocation SQF Quad Stand Installation | 15 d | Tue 3/7/06 | Mon 3/27/06 | AD Mechanical Technician[20%],AD Mechanical Engineer[2%] | 100% |
| 418 | Booster Dump SQF Quad Installation | 1 d | Tue 3/28/06 | Tue 3/28/06 | AD Mechanical Technician[300%],AD Mechanical Engineer[30%] | 100% |
| 419 | Booster Dump Vacuum Spool Installation | 2 d | Mon 3/27/06 | Tue 3/28/06 | AD Mechanical Engineer[30%],AD Mechanical Technician[200%] | 100% |
| 420 | Booster Dump Relocation Issue Request for Proposals on Conduit Construction | 20 d | Fri 7/1/05 | Fri 7/29/05 | | 100% |
| 421 | Booster Dump Relocation Relocate Power Supplies | 39 d | Mon 2/27/06 | Thu 4/20/06 | AD Electrical Technician[51%],AD Electrical Engineer[51%] | 100% |
| 422 | Booster Dump Relocation Install Conduit | 30 d | Tue 2/28/06 | Mon 4/10/06 | AD Electrical Engineer[50%],M&S[130,000] | 100% |
| 423 | Booster Dump Relocation Remove Beam Pipe @Conduit Core Location | 1 d | Mon 3/27/06 | Mon 3/27/06 | AD Mechanical Technician[200%],AD Mechanical Engineer[25%] | 100% |
| 424 | Booster Dump Relocation Terminate/Splice Cables/Controls | 3 d | Tue 4/11/06 | Thu 4/13/06 | AD Electrical Technician[300%] | 100% |
| 425 | Booster Dump Relocation Install Dump | 2 d | Mon 3/27/06 | Tue 3/28/06 | AD Mechanical Technician[400%],AD Mechanical Engineer[44%],M&S[7,000] | 100% |
| 426 | Booster Dump Relocation Radiation Safety Modifications | 250 d | Mon 5/16/05 | Fri 5/12/06 | | 100% |
| 427 | Booster Dump Relocation Install Dump Switch for V803 | 32 d | Wed 3/1/06 | Thu 4/13/06 | AD Mechanical Technician[9%],AD Mechanical Engineer[1%],M&S[10,000] | 100% |
| 428 | Booster Dump Relocation Pull Cables for V803 | 10 d | Fri 4/14/06 | Thu 4/27/06 | AD Electrical Engineer[200%],M&S[4,000] | 100% |
| 429 | Booster Dump Relocation Deleted Activity UID 788 | 1 d | Fri 9/30/05 | Fri 9/30/05 | | 100% |
| 430 | Booster Dump Relocation Beam Stop Design/Fabrication | 98 d | Mon 5/16/05 | Mon 10/3/05 | AD Mechanical Engineer[10%],AD Drafter/Designer[10%],AD Mechanical Technician[25%],M&S[8,000] | 100% |
| 431 | Booster Dump Relocation Install Beam Stop | 10 d | Tue 3/7/06 | Mon 3/20/06 | AD Mechanical Technician,AD Mechanical Engineer[20%],M&S[2,000] | 100% |
| 432 | Booster Dump Relocation Recable Interlock Chassis & Test | 10 d | Mon 5/1/06 | Fri 5/12/06 | AD Electrical Technician[150%],M&S[2,000] | 100% |
| 433 | Booster Dump Relocation Alignment | 2 d | Tue 4/11/06 | Wed 4/12/06 | PPD Survey Engineer[500%],PPD Survey Technician[1,000%] | 100% |
| 434 | Booster Dump Relocation Installation Complete | 0 d | Wed 4/12/06 | Wed 4/12/06 | | 100% |
| 435 | Budget Adjustment for Booster Dump Relocation Activities Already Closed | 22 d | Mon 5/1/06 | Wed 5/31/06 | AD Mechanical Engineer[481%],M&S[137,427] | 100% |
| 436 | Booster Chopper | |