| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 1 | Proton Plan | 1186 d | Thu 9/30/04 | Fri 4/17/09 | | 61% |
| 2 | Linac Upgrades | 682 d | Wed 12/15/04 | Fri 7/27/07 | | 65% |
| 3 | Linac PA Vulnerability | 488 d | Wed 12/15/04 | Mon 10/30/06 | | 88% |
| 4 | Linac Task Force Phase 1 Report Issued | 0 d | Mon 2/14/05 | Mon 2/14/05 | | 100% |
| 5 | Linac Quad Power Supplies | 669 d | Mon 1/3/05 | Fri 7/27/07 | | 62% |
| 6 | Linac Quad PS Upgrade Installation Complete | 0 d | Fri 7/27/07 | Fri 7/27/07 | | 0% |
| 7 | 200 Mhz LLRF Upgrade | 474 d | Mon 10/3/05 | Fri 7/27/07 | | 45% |
| 8 | 200 Mhz LLRF Installation Complete | 0 d | Fri 7/27/07 | Fri 7/27/07 | | 0% |
| 9 | Booster Upgrades | 1186 d | Thu 9/30/04 | Fri 4/17/09 | | 57% |
| 10 | Booster RF Duty Cycle Limits & Means of Improving Booster RF Reliability for 9Hz Operation | 251 d | Mon 8/22/05 | Tue 8/8/06 | | 90% |
| 11 | Booster RF Report Issued | 0 d | Tue 8/8/06 | Tue 8/8/06 | | 0% |
| 12 | OrBump System | 444 d | Thu 9/30/04 | Wed 6/14/06 | | 100% |
| 13 | OrBump Magnets Ready for Install on Girder | 0 d | Tue 1/31/06 | Tue 1/31/06 | | 100% |
| 14 | OrBump Girder Assy Complete | 0 d | Fri 4/7/06 | Fri 4/7/06 | | 100% |
| 15 | OrBump System Installation Complete | 0 d | Thu 5/11/06 | Thu 5/11/06 | | 100% |
| 16 | Corrector System | 1118 d | Tue 1/4/05 | Fri 4/17/09 | | 37% |
| 17 | Corr Prototype Design Complete | 0 d | Tue 10/31/06 | Tue 10/31/06 | | 0% |
| 18 | Long Straight Magnets Ready for Installation | 0 d | Tue 5/29/07 | Tue 5/29/07 | | 0% |
| 19 | DD: Prototype Approval | 0 d | Fri 11/10/06 | Fri 11/10/06 | | 0% |
| 20 | Short Straight Magnets Ready for Installation | 0 d | Mon 5/5/08 | Mon 5/5/08 | | 0% |
| 21 | Corrector System Complete | 0 d | Fri 4/17/09 | Fri 4/17/09 | | 0% |
| 22 | Long Straight Corrector AIPs Approved | 0 d | Mon 8/21/06 | Mon 8/21/06 | | 0% |
| 23 | Short Straight Corrector AIPs Approved | 0 d | Tue 5/1/07 | Tue 5/1/07 | | 0% |
| 24 | Gamma-t System | 844 d | Mon 5/2/05 | Fri 7/25/08 | | 36% |
| 25 | New Gamma-t Installation Complete | 0 d | Fri 7/25/08 | Fri 7/25/08 | | 0% |
| 26 | Booster RF Cavity Cooling | 343 d | Tue 1/4/05 | Fri 4/28/06 | | 100% |
| 27 | Booster Solid State RF Upgrade | 519 d | Mon 10/3/05 | Fri 9/28/07 | | 42% |
| 28 | Booster Dump Relocation | 282 d | Mon 5/2/05 | Wed 5/31/06 | | 100% |
| 29 | Booster Dump Relocation Installation Complete | 0 d | Wed 4/12/06 | Wed 4/12/06 | | 100% |
| 30 | Booster Chopper | 258 d | Tue 8/1/06 | Fri 7/27/07 | | 0% |
| 31 | Booster Chopper Installed | 0 d | Fri 7/27/07 | Fri 7/27/07 | | 0% |
| 32 | Booster RF Reliability Improvements | 184 d | Thu 9/1/05 | Wed 5/17/06 | | 100% |
| 33 | Main Injector Upgrades | 996 d | Thu 9/30/04 | Fri 7/25/08 | | 66% |
| 34 | Large Aperture Quads - WQB | 511 d | Thu 9/30/04 | Fri 9/15/06 | | 92% |
| 35 | WQB Design Complete | 0 d | Mon 8/15/05 | Mon 8/15/05 | | 100% |
| 36 | WQB Ready for Installation | 0 d | Fri 2/10/06 | Fri 2/10/06 | | 100% |
| 37 | WQB Align/Install Complete | 0 d | Mon 5/15/06 | Mon 5/15/06 | | 100% |
| 38 | WQB P.S. Ready for Installation | 0 d | Wed 3/1/06 | Wed 3/1/06 | | 100% |
| 39 | WQB P.S. Installation Complete | 0 d | Mon 5/22/06 | Mon 5/22/06 | | 100% |
| 40 | WQBs System Installed | 0 d | Mon 5/22/06 | Mon 5/22/06 | | 100% |
| 41 | Collimation Systems | 691 d | Tue 2/1/05 | Wed 9/26/07 | | 53% |
| 42 | MI-8 Collimators Installation Complete | 0 d | Fri 6/30/06 | Fri 6/30/06 | | 100% |
| 43 | MI Collimation System Install/Align Complete | 0 d | Fri 6/22/07 | Fri 6/22/07 | | 0% |
| 44 | Main Injector Loss Mitigation Complete | 0 d | Wed 9/26/07 | Wed 9/26/07 | | 0% |
| 45 | NuMI Multibatch Operation | 564 d | Mon 2/7/05 | Fri 4/6/07 | | 65% |
| 46 | Slip Stacking for NuMI Complete | 0 d | Mon 3/26/07 | Mon 3/26/07 | | 0% |
| 47 | Barrier Bucket Cavity Installation Complete | 0 d | Mon 4/24/06 | Mon 4/24/06 | | 100% |
| 48 | Injection Kicker Mod Ready for Installation | 0 d | Fri 4/21/06 | Fri 4/21/06 | | 100% |
| 49 | Injection Kicker Mods Complete | 0 d | Fri 4/28/06 | Fri 4/28/06 | | 100% |
| 50 | Main Injector RF Upgrade | 539 d | Tue 3/1/05 | Mon 3/26/07 | | 60% |
| 51 | MI RF Cavity Prototype Decision | 0 d | Tue 8/16/05 | Tue 8/16/05 | | 100% |
| 52 | MI RF Upgrade Scope Decision | 0 d | Mon 7/31/06 | Mon 7/31/06 | | 0% |
| 53 | MI RF Cavity Protection Syst Complete | 0 d | Thu 12/28/06 | Thu 12/28/06 | | 0% |
| 54 | General | 260 d | Fri 7/27/07 | Fri 7/25/08 | | 0% |
| 55 | Start 2007 Shutdown | 0 d | Fri 7/27/07 | Fri 7/27/07 | | 0% |
| 56 | Finish 2007 Shutdown | 0 d | Fri 7/27/07 | Fri 7/27/07 | | 0% |
| 57 | Start 2008 Shutdown | 0 d | Fri 7/25/08 | Fri 7/25/08 | | 0% |
| 58 | Finish 2008 Shutdown | 0 d | Fri 7/25/08 | Fri 7/25/08 | | 0% |