Proton Plan Master Schedule





Project Start:
Project Finish:
Tue 8/8/06
Fri 4/17/09


Tasks


ID
Task Name
DurationStartFinishResource Names% Complete
1
Proton Plan
1186 dThu 9/30/04Fri 4/17/09 61%
2
Linac Upgrades
682 dWed 12/15/04Fri 7/27/07 65%
3
Linac PA Vulnerability
488 dWed 12/15/04Mon 10/30/06 88%
4
Linac Task Force Phase 1 Report Issued
0 dMon 2/14/05Mon 2/14/05 100%
5
Linac Quad Power Supplies
669 dMon 1/3/05Fri 7/27/07 62%
6
Linac Quad PS Upgrade Installation Complete
0 dFri 7/27/07Fri 7/27/07 0%
7
200 Mhz LLRF Upgrade
474 dMon 10/3/05Fri 7/27/07 45%
8
200 Mhz LLRF Installation Complete
0 dFri 7/27/07Fri 7/27/07 0%
9
Booster Upgrades
1186 dThu 9/30/04Fri 4/17/09 57%
10
Booster RF Duty Cycle Limits & Means of Improving Booster RF Reliability for 9Hz Operation
251 dMon 8/22/05Tue 8/8/06 90%
11
Booster RF Report Issued
0 dTue 8/8/06Tue 8/8/06 0%
12
OrBump System
444 dThu 9/30/04Wed 6/14/06 100%
13
OrBump Magnets Ready for Install on Girder
0 dTue 1/31/06Tue 1/31/06 100%
14
OrBump Girder Assy Complete
0 dFri 4/7/06Fri 4/7/06 100%
15
OrBump System Installation Complete
0 dThu 5/11/06Thu 5/11/06 100%
16
Corrector System
1118 dTue 1/4/05Fri 4/17/09 37%
17
Corr Prototype Design Complete
0 dTue 10/31/06Tue 10/31/06 0%
18
Long Straight Magnets Ready for Installation
0 dTue 5/29/07Tue 5/29/07 0%
19
DD: Prototype Approval
0 dFri 11/10/06Fri 11/10/06 0%
20
Short Straight Magnets Ready for Installation
0 dMon 5/5/08Mon 5/5/08 0%
21
Corrector System Complete
0 dFri 4/17/09Fri 4/17/09 0%
22
Long Straight Corrector AIPs Approved
0 dMon 8/21/06Mon 8/21/06 0%
23
Short Straight Corrector AIPs Approved
0 dTue 5/1/07Tue 5/1/07 0%
24
Gamma-t System
844 dMon 5/2/05Fri 7/25/08 36%
25
New Gamma-t Installation Complete
0 dFri 7/25/08Fri 7/25/08 0%
26
Booster RF Cavity Cooling
343 dTue 1/4/05Fri 4/28/06 100%
27
Booster Solid State RF Upgrade
519 dMon 10/3/05Fri 9/28/07 42%
28
Booster Dump Relocation
282 dMon 5/2/05Wed 5/31/06 100%
29
Booster Dump Relocation Installation Complete
0 dWed 4/12/06Wed 4/12/06 100%
30
Booster Chopper
258 dTue 8/1/06Fri 7/27/07 0%
31
Booster Chopper Installed
0 dFri 7/27/07Fri 7/27/07 0%
32
Booster RF Reliability Improvements
184 dThu 9/1/05Wed 5/17/06 100%
33
Main Injector Upgrades
996 dThu 9/30/04Fri 7/25/08 66%
34
Large Aperture Quads - WQB
511 dThu 9/30/04Fri 9/15/06 92%
35
WQB Design Complete
0 dMon 8/15/05Mon 8/15/05 100%
36
WQB Ready for Installation
0 dFri 2/10/06Fri 2/10/06 100%
37
WQB Align/Install Complete
0 dMon 5/15/06Mon 5/15/06 100%
38
WQB P.S. Ready for Installation
0 dWed 3/1/06Wed 3/1/06 100%
39
WQB P.S. Installation Complete
0 dMon 5/22/06Mon 5/22/06 100%
40
WQBs System Installed
0 dMon 5/22/06Mon 5/22/06 100%
41
Collimation Systems
691 dTue 2/1/05Wed 9/26/07 53%
42
MI-8 Collimators Installation Complete
0 dFri 6/30/06Fri 6/30/06 100%
43
MI Collimation System Install/Align Complete
0 dFri 6/22/07Fri 6/22/07 0%
44
Main Injector Loss Mitigation Complete
0 dWed 9/26/07Wed 9/26/07 0%
45
NuMI Multibatch Operation
564 dMon 2/7/05Fri 4/6/07 65%
46
Slip Stacking for NuMI Complete
0 dMon 3/26/07Mon 3/26/07 0%
47
Barrier Bucket Cavity Installation Complete
0 dMon 4/24/06Mon 4/24/06 100%
48
Injection Kicker Mod Ready for Installation
0 dFri 4/21/06Fri 4/21/06 100%
49
Injection Kicker Mods Complete
0 dFri 4/28/06Fri 4/28/06 100%
50
Main Injector RF Upgrade
539 dTue 3/1/05Mon 3/26/07 60%
51
MI RF Cavity Prototype Decision
0 dTue 8/16/05Tue 8/16/05 100%
52
MI RF Upgrade Scope Decision
0 dMon 7/31/06Mon 7/31/06 0%
53
MI RF Cavity Protection Syst Complete
0 dThu 12/28/06Thu 12/28/06 0%
54
General
260 dFri 7/27/07Fri 7/25/08 0%
55
Start 2007 Shutdown
0 dFri 7/27/07Fri 7/27/07 0%
56
Finish 2007 Shutdown
0 dFri 7/27/07Fri 7/27/07 0%
57
Start 2008 Shutdown
0 dFri 7/25/08Fri 7/25/08 0%
58
Finish 2008 Shutdown
0 dFri 7/25/08Fri 7/25/08 0%

Resources


IDNameGroupMax UnitsPeak Units

Assignments


Task IDTask NameResource NameWorkStartFinish% Work Complete